← AWS Solutions Architect Professional: complex decisions
07 / 25 · 45 MIN

Discovery and migration waves

Connect technical strategy to dependencies, capacity, and business calendars.

Concept and mechanism

A server inventory is a starting point, not a complete migration plan. Add applications, interfaces, owners, criticality, business cycles, and support conditions. A monthly file may not appear in a daily-close rehearsal.

Group work according to dependencies and coexistence risks, not only operating system or CPU usage. The strategies known as seven Rs help decisions: rehost, relocate, replatform, repurchase, refactor, retain, and retire. The choice needs rationale and criteria.

Temporarily retaining an application with an unresolved physical dependency may be appropriate with defined review and responsibility.

Guided application

For rehosting compatible servers, current documentation names AWS Transform MGN for the service also known as Application Migration Service. Block replication supports the move; it does not rewrite a monolith or establish functional compatibility.

Replatform may preserve core logic while moving operations to a managed platform. Rewriting and migrating simultaneously can increase complexity, so benefit should justify risk. Also plan human capacity: four calendar weeks from someone allocated at 25% are not four full-time project weeks.

Include RUN, backup owners, rehearsals, windows, and acceptance decisions in the wave plan.

Choose compute with host dependencies

Inventory host dependencies before choosing where a container runs. Distinguish API permissions, process capabilities, and device access. A more permissive IAM policy does not add runtime capabilities.

If a host dependency is mandatory, retain a platform that supports it and name who prepares, updates, and recovers hosts. A managed alternative enters the plan after removing and validating that dependency. Include the operational cost accompanying flexibility.

Reduce operations while retaining application ownership

Use trial results to decide whether the application can move to managed compute. Record removed dependencies and remaining responsibilities. Reducing host maintenance does not eliminate library updates, secret management, or validation of new images.

Compare proposals against the stated operational objective; adding another orchestration platform without a concrete need can increase work. Acceptance covers behavior, recovery, and cost under relevant load.

IN PRACTICE

Three applications use the same close files. The first wave must prepare the complete flow or the hybrid dependency during coexistence.

Common pitfalls

Server as service; copy as acceptance; cloud as mandatory decision; effort as calendar duration.

Related topics: Data, cutover, and transition to RUN · Organization, identity, and controls

Take this idea with you

Choose strategy and sequence from real dependencies and available capacity.

Create account

References

AWS is a trademark of Amazon.com, Inc. or its affiliates. bigsavant.com is an independent preparation platform and is not affiliated with, associated with, sponsored, authorised or endorsed by AWS. Content and questions are original, are not official exam questions, and completing our tests does not award or guarantee any certification. Names are used only to identify the subject. All other trademarks belong to their respective owners.