← CBAP: requirements, decisions, and business value
20 / 28 · 175 MIN

Capacity, flow and service options

Model visits, resources and batches to compare service alternatives with explicit deadlines, effort, value and uncertainty.

Start with the decision and the unit

Imagine an analysis team evaluating the next design for receiving fund instructions. “We need more capacity” does not yet specify the decision: completing more instructions daily, meeting urgent deadlines, reducing customer effort or freeing APS time may favor different options. Write the intended outcome, horizon, constraints and selection criterion before calculating. A useful recommendation explains the need it addresses and what it sacrifices.

Distinguish a unique request, a visit to a task, a minute of resource occupancy, a completed output and elapsed time. An instruction can visit one team twice; an operator can perform two stages; a batch can finish several instructions together. These facts change the model. Record the boundary too: application, complete process or service including suppliers. This lesson’s figures are fictional and deterministic. Simplification exposes decisions; it does not automatically estimate real waiting times, availability or service levels.

Count work that returns

In a separate example, 80 requests need four minutes of initial review. Twelve return exactly once for a three-minute review, with no later returns. Workload is 80×4+12×3=356 minutes. Request count remains 80. The 92 visits explain workload, not 92 customer outcomes. Do not subtract corrected requests: they already occupied the resource on their first visit.

If the team only says “15% return,” details are missing. Is the percentage of original requests or all visits? Does the return take the same time? Can a second return occur? The answers can change the design of training, source validation or review capacity. Use traceable counts and state the model’s boundary. Use indefinite repetition only if that mechanism is defined; a more sophisticated formula can be less faithful than a table of actually observed visits.

Diagram boxes are not additional resources

A preparation stage takes two minutes and confirmation takes four. If one person performs both without overlap, each request uses six minutes of that person’s time. In 60 minutes, theoretical capacity is ten requests. Taking the smaller of 30 preparations/hour and 15 confirmations/hour would give 15 and ignore that both rates compete for the same time. With two dedicated people, one per stage, the model changes: as sustained capacity under the stated conditions, confirmation limits the chain to 15.

Add resources, qualifications, schedules and actual concurrency to the design. Resource occupancy need not equal an instruction’s elapsed time, which may include waiting. These examples exclude breaks, variability, buffer blocking and failures. In a real analysis, investigate those conditions before treating calculated capacity as a commercial commitment.

Recalculate the limit after each option

In a simple chain with independent resources, no losses and no rework, every output requires one visit to every stage. A lower-capacity stage prevents the others from converting all their capacity into output. Demand can also limit actual production. For example, with demand 90 and stage capacities 100, 70 and 85 per hour, output is bounded at 70. Raising the second stage to 95 moves the limit to 85; it does not create 25 additional outputs per hour.

Compare every option with the same reference. If raising the second stage to 85 costs less than raising it to 95 and the only objective is this model’s output, the extra capacity delivers no additional benefit. Other reasons, such as later growth, may justify buying it, but need their own horizon and evidence. Also record that restricting input can contain work in progress without increasing output. Queue control and capacity growth are different effects.

Translate demand into effort and allocation

One hundred requests do not define one hundred equal units of effort. If 70 standard requests need two minutes and 30 specialist requests seven, workload is 350 minutes. At 50 of each, it becomes 450 without increasing request count. Compare automation proposals in the class they actually change and retain required controls. Removing one minute from a rare class can release less capacity than a modest improvement in a frequent class.

Nominal capacity is not interchangeable by default either. If only one person can perform a specialist task, another person’s spare time does not remove that constraint. Build a small person–task matrix and try feasible assignments. An additional objective, such as preserving a training block, belongs in the criterion. Do not assign work through equal request counts when times, qualifications or required continuity differ.

Compare setup economy with delivery deadlines

A batch can reduce setup work per instruction while increasing time to the first released response. Define whether outputs become available per instruction or only at batch completion. On a machine requiring four setup minutes plus one minute per instruction, a batch of eight finishes in 12 minutes. Two batches of four finish at eight and 16 minutes: they consume more total time but release the first four responses sooner.

The choice depends on deadlines and order. Draw a timeline showing request availability, setup start, processing and result release. Do not use average capacity or total duration alone. In these exercises, setup occupies the same machine and batches cannot overlap. If a supplier can prepare the next batch in parallel, that is a new assumption to model and demonstrate, not an implicit benefit.

Compare value while retaining commitments

An option with higher value per request can consume so much resource that total value is lower. Where the model permits comparison, calculate value per unit of the limiting resource. First retain mandatory minima, dependencies and other conditions. If one service takes three minutes per request and yields nine points, while another takes six and yields 12, the first yields three points per minute and the second two. This can guide remaining capacity only when points are comparable and additive and demand exists.

Do not generalize this rule to every portfolio. Indivisible requests, customer minima, different resources and overlapping benefits may require enumerating feasible sets. Here, points are fictional preferences, not revenue or financial return. Deliver the criterion, mix, resource use and retained commitments with the recommendation; an isolated ranking does not establish feasibility.

Retain dependency between scenarios

A forecast may provide an interval without probabilities. Do not automatically turn its midpoint into an expected value. Ask which decision the interval must support: best case, a commitment covering every admitted case or investigation to reduce uncertainty. The criterion is a management choice that the model should expose.

If two request types always total 100, increasing one reduces the other. Adding their separate maxima creates an impossible mix. Write the relationship, such as standard=100−specialist, and calculate each scenario using compatible values. A reservation covering the interval maximum is sufficient only for the stated assumptions: constant times, no additional work and the supplied availability. It does not cover occurrences omitted from the interval. Distinguish an explicitly required margin from extra capacity purchased without defined benefit.

Design the sequence of commitment and learning

A staged strategy benefits from new information only if a decision remains that the information can change. Distinguish reserving capacity, activating it and paying for use. A contract can give each step a different deadline and cost. If reservation closes before demand becomes known, “wait and decide later” can destroy the very alternative intended to be preserved.

Original example: a reservation costs one unit today; activation tomorrow costs three more. Tomorrow’s information can avoid activation under low demand. With equivalent fixed capacity costing five units, the reserved option costs one or four and is cheaper in both scenarios if it meets the same requirements. But if activation were also required today, that benefit from waiting disappears. Represent intermediate states and deadlines instead of treating “staged” as a guarantee of flexibility. Do not invent probabilities to compare an option already dominating in every supplied scenario.

Relate the error unit to the business outcome

A rejection can have a broader boundary than necessary. If the contract permits independent instruction decisions and requires individual outcomes, rejecting a whole batch for an isolated error prevents valid results. More CPU does not change that behavior. Analysis should specify which units are independent, which depend on each other and which response accompanies each decision.

Partial acceptance does not mean hiding invalid instructions or accepting them without controls. The design should retain an outcome for every received instruction and identify those needing correction. If a genuine all-or-nothing obligation exists, such as an explicitly indivisible set, separating instructions can violate the requirement. This lesson does not prescribe universal partial acceptance: it teaches comparing the implemented boundary with the business boundary before choosing a technical solution.

Identify who receives work and compare future costs

A local improvement can transfer effort. Show before/after by stakeholder and resource instead of calling every observed reduction a saving. If customers save six minutes but the processing team adds four, total effort falls by two while team spare capacity decreases. Both conclusions can be true. The solution boundary helps classify the limitation and involve those controlling the external process, without assuming the whole organization is inside the application.

When recommending retention, replacement or retirement, compare costs and outcomes that can still change within the horizon. An unrecoverable investment belongs to both options’ history, but migration, exit and future operation still count. A cheaper alternative is comparable only if it retains relevant capabilities and obligations. Recognizing past costs is not a shortcut around transition analysis. Financial criteria and operational sufficiency both need to be explicit.

Guided exercise: retain the design and change assumptions

Use a spreadsheet or paper. A fictional day has 90 requests. Each needs three minutes of initial review. Eighteen require one additional two-minute review. The team has 300 minutes; all other stages have sufficient capacity. Option P reduces returns to nine requests while keeping times. Option Q reduces initial review to 2.8 minutes while keeping 18 returns. Both cost the same and retain controls. Calculate current workload and each option’s workload, then recommend the one leaving most spare capacity in this model.

Solution: current=90×3+18×2=306; P=270+18=288; Q=252+36=288. It is a tie, with 12 spare minutes. Do not invent a numerical preference: record the tie and identify a relevant additional criterion. Variant A: returns become 30 and P halves them; current=330, P=300 and Q=312. Only P fits. Variant B: returns revert to 18 but each additional review takes four minutes; current=342, P=306 and Q=324. Neither option fits 300.

Explain why the initial recommendation cannot simply be copied into the variants. Results depend on visit count and duration. These bounded calculations check consistency of assumptions; they are neither a production capacity test nor evidence that controls are effective.

Conditional risk and common causes

Redundancy needs a dependency model. Suppose a 5% common failure disables two providers. When that failure is absent, each provider fails with 10% probability, independently of the other. Joint loss probability is 0.05+0.95×0.10×0.10=0.0595. Multiplying only 0.10×0.10 omits the common cause; adding 0.05+0.01 applies the second branch to cases already counted in the first. Draw mutually exclusive branches before calculating.

Mitigation can reduce the common cause, individual failures or consequence. Record which component changes and the certain cost added. If the agreed decision rule uses cost plus expected loss, include both. A rule with a separate probability or impact limit also needs that check. These figures are fictional; they do not characterize real-provider availability. Before applying the reasoning at work, verify probability provenance, event dependence and the conditions under which estimates were obtained. Also check whether the alternative provider uses the same identity service, power supply or recovery team. Two contracts do not establish two independent capabilities. A change in this boundary requires revisiting model branches, not merely substituting a percentage.

Imperfect information and decisions that can still change

Information value comes from decisions it can improve. A diagnostic may leave physical failure probability unchanged and still help choose whether to proceed. Construct four rows: failure with alert, failure without alert, readiness with alert and readiness without alert. In each row multiply state probability by signal probability within that state. Then group by signal and compare actions. Do not confuse P(alert given failure) with P(failure given alert).

Example: initial failure probability 20%, diagnostic alert in 75% of failures and 25% of ready cases. Joint probabilities are 0.15;0.05;0.20;0.60. With alert, failure probability is 0.15/0.35; without alert, 0.05/0.65. If proceeding loses 100 on failure and delaying costs 30, delay on alert and proceed otherwise. Expected cost before diagnostic price is 0.35×30+0.05×100=15.5. Without information, the best action costs 20. Thus the maximum price giving a tie is 4.5 under these premises. A more expensive diagnostic may not pay.

Information also has a deadline. If it arrives after an irrevocable reservation, it cannot improve that past decision. Specify an observable signal, owner, time and still-available action. Already irrecoverable cost must be treated consistently across options; adding it only to stopping or only to continuing distorts the choice.

Uncertainty without a distribution and authority limits

A probability interval does not authorize automatically choosing its midpoint. If the decision maker requests lowest expected cost at the worst admissible p, calculate that worst value for each option. Minimizing maximum regret is a different rule and may choose differently. State the rule before ranking alternatives. A mean calculated using invented p conveys unsupported precision.

Keep three judgments separate: an option meets modeled limits; its dependencies are available; someone has authority to accept it. Mitigation dependent on a pending license can have acceptable modeled residual risk yet remain unavailable for activation. A recommendation may be conditional, with a verifiable condition, owner and useful date.

Workshop: write a tree containing a common cause and individual failures, compare two mitigations and change just one probability. Add a limit that cost cannot offset. Then place a diagnostic before or after the decision deadline. Explain which choices change and why. Check calculations by enumerating rows before writing the recommendation. Summary: preserve dependencies, conditioning, information price, timing and authority. Correct arithmetic on an incorrect model still produces a poorly supported decision.

Build capacity within the required window

Specify the timing boundary the option must support. Publishing a change within fifteen minutes of its source occurrence includes polling wait, preparation and publication. If the source permits polling only and stages take four and three minutes sequentially, an eight-minute interval gives an upper bound of fifteen. Ten can allow seventeen. Declaring dependent stages simultaneous without changing their actual dependency does not create an executable option. This is a deterministic teaching model rather than observed service latency estimation.

Shared capacity must include all concurrent consumers. Thirty four-unit requests and twenty two-unit requests need one hundred sixty units in the same interval. Comparing one hundred twenty and forty independently with one hundred fifty capacity uses the same resource twice. If resources are not interchangeable, preserve separate bounds.

Capacity’s calendar position matters as much as total quantity. Forty six-minute decisions require two hundred forty human minutes. Within one hour, four operators can each finish ten in the loss-free model; two cannot. Availability the next morning does not meet the night deadline. Workshop: draw the permitted worst case, add only sequential stages and allocate resources within the window. Then introduce variability and identify missing evidence before committing real capacity.

Complete paths under individual failures

Counting redundant components does not establish that a complete path remains available. In the model, a query requires identity and directory providers. Paths(A,D) and(B,D) use distinct identities but share directory D. D failure removes both. Another frontend or a third identity provider still does not remove that common dependency.

The(A,D) and(B,E) option has separate paths for the declared component set. An individual A or D failure leaves(B,E); a B or E failure leaves(A,D). This conclusion depends on compatibility and available-path selection, both required design work. If policy required every component’s agreement, the same structure would not meet the objective. If A and B depended on unmodeled common infrastructure, include it in analysis.

Workshop: write a matrix with one unavailable component per row and one path per column. Mark a path available only when all its components are available. Then ask whether one path is sufficient or policy requires several. Add a common dependency and repeat. Summary: allocation must preserve the outcome under selected failure conditions. This exercise establishes neither real-service independence, failure probabilities nor measured availability; it teaches testing an option’s logic before implementation.

Unknown dependence and tolerance

If a service fails only when two components fail together, knowing their individual probabilities does not justify multiplication. The product corresponds to independence. When dependence is unknown, retain that uncertainty. Joint probability lies between max(0,pA+pB−1) and min(pA,pB). The upper bound follows because joint failure is contained in each individual failure; the lower bound prevents the union from exceeding probability one.

In a fictional example, pA=10% and pB=25%. Interruption at 2.5% is compatible with independence, but every A failure could also occur within B failures, producing 10%. If tolerance requires at most 6% under any dependence, reducing A to 4% demonstrates that bound without changing B. Reducing B to 8% does not: an 8% intersection remains compatible with the marginals.

Decision policy matters. An organization may request an estimate with explicit assumptions or a bound robust to every admitted dependence; these are different commitments. In this exercise, marginal reductions are guaranteed premises. For an actual decision, investigate whether mitigation also changes other failures, how probabilities were estimated and the observation period. Do not turn a point estimate into a guarantee. To practise, draw four cells: both fail, A only, B only and neither. Construct a compatible table at each extreme and compare costs of mitigations satisfying tolerance.

Find the worst case within the allowed set

A capacity promise needs a defined demand set. Adding separate maxima may create an impossible scenario; checking only those endpoints may miss a more demanding combination. Retain relationships between variables and include costs activated by thresholds. Do not replace that set with an average without an explicit risk-acceptance decision.

Example: total work is 100+20x+30y minutes, with nonnegative integers x and y and x+y≤3. If x≥1, preparation adds 35 minutes. For x=0,1,2,3, the largest permitted y is 3,2,1,0. Maximum totals are 190,215,205,195 minutes. The worst case is x=1,y=2 at 215 minutes, neither isolated endpoint. The preparation discontinuity explains the difference.

This proof depends on the capacity contract. Aggregate effort minutes do not guarantee a deadline if only one person is authorized, tasks are indivisible, arrivals are late or windows differ. State whether work can be distributed and whether precedence constraints exist before treating a sum as sufficient capacity. A request’s age is elapsed time, not remaining work.

Workshop: enumerate allowed combinations, calculate work and identify a witness attaining the maximum. Add an assumption that preparation is already complete and recalculate; do not retain the old reserve by habit. Then introduce an execution window and explain what effort enumeration no longer establishes. Summary: connect the recommendation to its assumptions, limiting scenario and signals requiring reconsideration.

Preserve identity across stages

The mean of two stages’ sum can be obtained by adding their means when they describe the same requests. The proportion meeting a deadline also depends on how stage times combine for each request. Keeping only separate histograms loses that relationship. A comfortable mean can coexist with a group repeatedly exceeding the limit.

Example: among twenty requests, the first stage takes one minute for eighteen and seven for two. The second takes two minutes for eighteen and six for two. The total limit is ten minutes. If the two slow groups coincide, those two requests take thirteen minutes and only eighteen meet the limit. If the groups are disjoint, the largest totals are nine and seven, and all meet it. Both scenarios have a four-minute total mean. A target of nineteen out of twenty cannot be confirmed from the histograms.

An intervention capping the first stage at four minutes caps every total at ten in this model. That is a property of the supplied projection, not proof of actual performance. A trial must measure both stages under a common identity and confirm the change’s effects, volume conditions and retained controls. If additional waits exist outside the two stages, the conclusion requires revision.

Workshop: construct two twenty-row tables with identical histograms and different pairings. Calculate mean and count meeting the deadline. Compare an improvement to the fast stage with one to the slow stage and check the worst pairing as well as cost. Summary: choose evidence answering the criterion; total mean and the proportion of requests meeting a deadline are different measures.

Check composition against the failure set

Redundancy should answer a defined failure set. Counting components or paths is insufficient. A common domain may remove several components at once; simultaneous maintenance may eliminate the only remaining alternative. Describe what must remain available and which unavailability combinations belong to the obligation.

Example: two domains each contain one identity provider and one directory. Every pairing is compatible and a query requires both types. Losing one domain leaves one identity provider and one directory. If the requirement also allows maintenance of the surviving identity provider, no path is possible. Preconfiguring all four pairings does not resolve the absence of an available component of the required type. Another capability, another operating condition or an authorized requirement change is needed.

Adding a third domain with both types allows three complete paths, one per domain, to tolerate loss of one domain plus maintenance of a component outside it in this model. One path disappears with the domain, another may disappear with maintenance and the third remains. This does not mean every three-path set works: distributing endpoints across domains may cause the same failure to affect two paths.

To validate an option, list every allowed failure, mark unavailable components and seek a permitted complete path. Retain at least one counterexample for each rejected alternative. Define path selection, response equivalence and sufficient capacity; a surviving-component list does not show that a query can use them. Probabilities are needed only if the criterion calls for them; a guarantee over all combinations requires checking them even when some are rare.

Workshop: draw all four pairings across two domains and apply the stated failure and maintenance. Then add the third and compare within-domain paths with cross-domain paths. Worked guidance: first establish whether remaining resources permit any solution, then whether configured paths supply it. Summary: composition must reflect actual dependencies and failure conditions without assuming independence merely because names or suppliers differ.

Retain impact dimensions in the assessment

A risk response may change one consequence without changing the others. Monetary compensation does not by itself imply faster recovery, meeting a deadline or capacity to serve customers. Identify the event, relevant consequences and each measure's actual effect. Apply approved limits before seeking the preferred alternative.

Fictional example with exclusive states: normal operation in 90% of cases, without loss or interruption; network failure in 8%, with loss 50 and one hour of interruption; common-service failure in 2%, with loss 300 and eight hours. Agreement F reduces loss in the last state to 30 without changing duration. Alternative path I reduces that loss to 60 and duration to one hour. Probabilities remain unchanged.

Expected loss with F is 0.08×50+0.02×30=4.6; with I it is 0.08×50+0.02×60=5.2. If the rule requires expected loss at most 6 and probability of interruption longer than two hours at most 1%, F meets the first criterion but fails the second at 2%. I meets both in this model. Selecting only the lowest monetary loss would recommend outside the rule. Measure price must also follow the decision contract, without omission or double counting.

Present an option matrix: price, retained loss, duration or another impact, availability conditions and necessary authority. State which events the response changes and which it leaves unchanged. A measure requiring a particular license, team or access is not available merely because its arithmetic fits; that condition must accompany the recommendation. Do not turn conditional acceptance into immediate authorization.

Workshop: add a proposal eliminating long interruption but exceeding the authorized budget. Worked guidance: it may justify requesting another decision but does not meet existing delegation. Summary: assessment must retain dimensions, limits and realization conditions. These numbers are teaching premises; they do not estimate a real service's risk or describe universal compensation-contract terms.

Exercise files

Original Python exercise with editable data, instructions and explained results. Requires Python 3.10 or later; no network or production data is used.

Download the capacity and decision exercise

SHA-256 (ZIP)

970373073ffc1fd46bd50add92d832510bc661b04e4046fe77b72b512310bbad

IN PRACTICE

A smaller batch can release urgent results earlier while consuming more setup. The right option depends on the output contract and each group’s deadlines.

Common pitfalls

Counting instructions instead of visits; duplicating one person’s capacity; buying beyond the next limit without benefit; adding incompatible maxima; optimizing total duration while ignoring deadlines; awaiting information after losing the option; confusing transferred work with eliminated work.

Related topics: Current-state analysis · Design options and value · Solution and enterprise limitations

Take this idea with you

A sound recommendation connects the desired outcome to the right unit, actual resources and each option’s conditions. Recalculate when assumptions change and communicate what the model can and cannot establish.

Create account

References

CBAP® is a registered trademark of International Institute of Business Analysis. bigsavant.com is an independent preparation platform and is not affiliated with, associated with, sponsored, authorised or endorsed by IIBA. Content and questions are original, are not official exam questions, and completing our tests does not award or guarantee any certification. Names are used only to identify the subject. All other trademarks belong to their respective owners.