← CBAP: requirements, decisions, and business value
06 / 28 · 170 MIN

Compare design options and value

Explain costs, gaps, assumptions, and recommendation trade-offs.

Concept and mechanism

A recommendation needs a consistent comparison. Buying, building, adapting, or retaining may be valid options depending on capabilities, constraints, and costs. Use the same horizon and identify exclusions in each estimate.

In a nondiscounted exercise, €120,000 upfront and €20,000 yearly total €180,000 over three years; €60,000 upfront and €50,000 yearly total €210,000. This compares costs under stated assumptions rather than proving the best solution by itself.

Include integration, operations, vendor exit, and retirement where relevant. Do not add incompatible benefits from the same resource: the same 300 hours cannot be removed from the team and simultaneously reused in full by it.

Guided application

Ninety percent feature coverage may hide a missing mandatory capability. Assess criticality and feasible ways to address gaps without automatic approval or rejecting every possible configuration. If an option violates a mandatory constraint, a high economic score does not make it admissible.

Seek a compliant alternative or authorized revision where revision is possible. Expose sensitivity: if small weight changes reverse the choice, decision makers should know that fragility. When decisive data is missing, a pilot with exit criteria may be more useful than artificial numerical precision.

Record the recommendation, its conditions, and the decision made by the authorized party.

Define a complete option and its boundary

An option should explain how the need will be met, including components outside the purchased product. A feature catalog does not necessarily describe a usable solution. If the requirement calls for recovery after supplier exit, retaining encrypted exports does not alone resolve format, decoder, usage rights, keys or loading time. Represent the complete path from archive to recovered service, with owners and commitments. Demonstrated six-hour loading of an open format covers only that stage.

Composition also needs meaning contracts. Two products covering different channels do not automatically produce one consolidated customer result. Identify customer, event, period and value unit before adding totals. The same event may occur on both channels or the same reference may have different values. The option needs combination and difference handling rather than a dashboard merely placing numbers side by side.

Workshop: draw one purchased option and one composed option. Mark supplied capabilities, complementary work, external dependencies and unconfirmed conditions in each. Add supplier exit and a case with unresolved identity. Explain what becomes unavailable and who should decide. Summary: component coverage is input to option definition; completeness depends on the path through to the required outcome.

Allocate requirements to releases and coexistence

A release needs a coherent intermediate state even when the final solution spans several releases. If the API arrives before its executor, ask what happens to accepted requests in the interval. Queuing them until release two does not meet a commitment to finish during release one. An adapter can connect the new channel to the old executor, but it needs request identity, decisions retained across retries and defined execution authority. First response does not automatically confer authority after both executors have acted.

Legacy retirement also depends on replacement capability. If historical queries remain required and conversion occurs only in release two, design must retain a permitted reading path. A possible license extension needs commitment, duration and owner; possibility does not mean it is already contracted. Copying files into a component without a compatible reader does not complete the path.

Workshop: write three states, before, during and after change. For each, identify who can accept, execute, query and recover requests. Record keys, versions and transition conditions. Add a retry during cutover and a historical query before conversion. Resolve where each requirement is met and which authority decisions remain pending. Allocation should make service possible while change remains incomplete.

Retain obligations in process options

Buying, automating and reorganizing are ways to realize a need. Changing the mechanism does not remove its conditions. If policy requires an authorized person’s human approval, automating preparation can reduce work without waiving that decision. An option automating both stages must resolve the approval rule or obtain authorized revision; a higher automation percentage does not itself make it compliant.

Describe remaining queues and work. Who handles a prepared request still awaiting decision? Which identity and state remain available when its owner changes teams? If confirmed capacity covers every request, do not invent a deficit to exclude the manual or hybrid option. Two descriptions buying preparation and retaining identical human approval may be equivalent for this allocation despite different commercial names.

Operations depend on actor state too. Current service may restrict reading to active contracts; retained data do not create former-customer access. Archive mode must define identity, permitted operations and access interval while retaining editing prohibition where required. Workshop: compare two options against the same need, separating preparation, decision, querying and recovery. Mark one retained obligation, one gap and one exception state. Use supplied rules rather than adding a legal duty or an undecided waiver.

Align decision and recovery units

An interface can retain every message yet decide repeatedly on the same request. Define the logical unit before specifying its adapter. Message identifiers may change on retry; equal content can merge distinct requests. Identify how messages associate with requests and what happens when identity remains unresolved. Amendments need explicit treatment too, preventing automatic confusion with retries or new requests.

Recovery needs a corresponding boundary. If requests must remain independent, one transaction for ten requests can erase earlier effects when the tenth fails. Ten report rows do not create ten transactions. If the component permits a separate instance per request, that option may align effect and rollback units, but external coordination still needs retained identity and results. Do not add joint atomicity when the need excludes that relationship.

Workshop: describe two executions of one request and a failure after data modification. Draw where the decision is retained, who has authority and which effects may roll back. Compare one transaction per batch with one per request. Explain what the model permits and which failure tests a concrete implementation needs. Summary: decisions, effects, retries and recovery need compatible units; result presentation does not repair an incorrect execution boundary.

Retain capacity over compatible paths

A resilient option must retain both function and required capacity. In the example, each query uses identity and a directory. A and B each supply 50 queries per hour; D and E each supply 90.

A reaches only D, while B reaches D or E. The objective requires 80 after any isolated failure. Without additions, losing A leaves only 50: a surviving path is insufficient.

Adding C with capacity 50 and a link to E changes the complete set. If D fails, B and C share E, capped at 90 rather than 180. If E fails, A and B share D, also capped at 90.

If B fails, A uses D and C uses E, supplying 100. Losing A or C also permits distributing 100 across surviving links. For each failure, write a feasible allocation and check that no component exceeds its aggregate capacity.

Then find a bound no allocation can exceed. This distinguishes a feasibility witness from an optimistic sum. Capacities and links are deterministic exercise premises; they demonstrate neither real failure independence, costs, latency nor operational recovery.

Those conditions require their own criteria and evidence before selecting a real solution.

Evaluate information that changes the decision

Information value depends on the decision it can change, not only apparent study accuracy. In the model, high demand has probability 0.4. Large is worth 120 in that state and −60 in low demand; small is worth 40 in either.

Values are thousands of euros net of all solution costs. Without information, 0.4×120+0.6×(−60)=12, so small is better. A study is positive in 75% of high states and 25% of low states.

Positive joint probabilities are 0.30 and 0.15, totaling 0.45. Among positives, the high share is 0.30/0.45=2/3 rather than 0.75. Large becomes worth 60 in that group.

Among negatives, small remains better. Large after positive and small after negative is worth 0.30×120+0.15×(−60)+0.55×40=49 before study cost. At cost eight, expected net value is 41 versus 40 for immediate selection.

A cost of nine produces a tie; at ten, immediate selection is better. These probabilities are supplied, not estimated from learners or suppliers. Recommendation depends on authorized expected-value criteria and absence of other limits; it guarantees no individual outcome and does not replace risk, timing or budget constraints when present.

Demonstrate assignment with authorization and absence

Nominal team capacity does not establish that a valid assignment exists. For approval requiring two distinct people, confirm identities, separation from the preparer, request-specific authorizations and available minutes. The same person holding two roles remains one person. Automating preparation does not change an explicit human-approval obligation.

In an example, two requests need two reviews each. U and V can review the first; V and W the second. Each person can perform two reviews within the window. U/V on the first and V/W on the second respect capacity and distinct identities. If V is absent, U and W still provide four reviews of aggregate capacity, but each request has only one authorized person. The total looks sufficient; the required assignment is impossible.

Adding U to the second request and W to the first permits U/W on both when V is absent. Each person performs two reviews. This establishes that absence scenario; a broader promise requires repeating the search for every admitted absence. As requests and authorizations grow, represent them in a matrix and seek complete assignments. Each request row needs the required number of distinct identities; each person column must respect capacity. Assignment may adapt when the scenario changes if the contract allows it.

Workshop: add a third request and a fourth person, limit each reviewer to two reviews, and seek an assignment for every single absence. Present a complete witness for feasible cases and a request lacking enough authorized reviewers for an impossible case. State duration, required ordering between reviews and any transfer time. Summary: developing an option includes who can do the work, when and under which failures; a sum of hours or an automation percentage does not establish these conditions.

Separate cost, commitment and cash

Compare alternatives for the same need while retaining each contract's conditions. Usage period, billed period and payment timing may differ. Retiring a solution after five months does not automatically remove a twelve-month obligation. Similarly, dividing an invoice into monthly amounts may aid accounting presentation without changing the amount paid.

Fictional example: a solution is needed for five months. A costs 10 for setup, 6 per started four-month block with a minimum of three blocks, and 2 for exit. B costs 14 for setup, 5 per started four-month block with no additional minimum, and 3 for exit. There is no proration. A's contracted cost is 10+18+2=30; B's is 14+10+3=27. A needs only two blocks for use but contractually pays three. B needs two because month five starts another block.

If setup and the first block are paid initially, A requires initial cash of 16 and B requires 19. With an initial cap of 18 and later funding secured, B is ineligible on current terms despite lower total cost. The analysis should present that distinction. Another payment schedule may be investigated, but a possible negotiation is not an obtained condition.

Prepare a table with payment event, amount, timing, cancellation possibility and triggering condition. Include migration, coexistence, operation and exit where applicable, without adding the same expense to two categories. If financial discounting applies, use the approved criterion and each flow's date; do not mix discounted totals for one alternative with nominal totals for another.

Workshop: repeat the comparison for nine months of use while retaining the cash cap. Worked guidance: A still pays for three blocks and costs 30; B now needs three and costs 32. Initial cash remains 16 and 19 if payment timing is unchanged. Summary: a recommendation should distinguish total cost, eligibility and negotiated conditions. These rules are exercise premises, not assumed terms for any supplier.

Connect each benefit to a feasible use

Freeing hours does not determine how benefit will be realized. Reducing contracted work, delivering additional work and retaining capacity reserve are different uses. The same hour cannot leave the team and remain available to produce value. Record the operational decision converting freed time into each outcome and the cost of enabling it.

Example: 100 hours become available. Up to three 30-hour blocks may be cancelled, saving 300 per block. New requests use ten hours and add 200 of net contribution each; demand is four. Any new work requires ten preparation hours once, within the same 100. Unused hours are permitted and have no other benefit in the model.

Compare by cancellation count. With zero or one block cancelled, four requests fit: benefits are 800 and 1100. With two blocks, 40 hours remain; preparation leaves room for three requests, yielding 600+600=1200. With three blocks, ten hours remain, insufficient to prepare and handle a request, so benefit is only 900. The best allocation is two blocks and three requests, accounting for 100 hours. The highest request count or cancellation count alone does not identify the best decision.

For an actual recommendation, confirm that hours can really be cancelled, skills permit allocation, demand exists and per-request benefit already deducts relevant costs. An hour freed on one shift may not serve demand on another. Net value should not deduct costs it already contains again, just as savings should not count hours used to produce that value a second time.

Workshop: reduce maximum demand to two requests. Worked guidance: two blocks and two requests use 90 hours and generate 1000, exceeding three cancelled blocks at 900. Ten unused hours do not invalidate the solution; there is no further admissible use that increases value in this model. Summary: validate allocation, units, preparation, limits and demand before adding benefits. Relate this analysis to operational capacity and change acceptance criteria.

Define consolidation semantics

An option composed of several products must explain how their outputs become the required result. Define entity identity, event identity, version and value semantics. These concepts solve different problems. Mapping two customer identifiers does not establish that two records describe the same event. Equal values do not establish duplication either.

Example: U and V are approved identifiers for the same customer. Records arrive as U/P/version 1/50, V/P/version 2/45 and V/Q/version 1/50. The contract says versions replace the entire prior value and different events are additive. Current result is P=45 plus Q=50, totaling 95. Retaining an old version for traceability does not mean including it in the total. If U/P/version 1 arrives again at the end, the total stays 95.

Describe the required component: resolve identity within authorized scope, group by the correct event, compare versions under a defined order and retain provenance. Also define what happens when identity has no mapping, one version has conflicting values or records are missing. Rejecting, isolating for investigation or publishing a partial result are decisions needing a contract; they should not be hidden in a silent sum.

Distinguishing replacement from incremental movement is essential. If 45 were a delta to add rather than a complete value, highest-version selection would not suffice. Cancellation also needs defined semantics: a cancellation marker may prevent an old copy recreating an event. These behaviors are not universal; the option must specify them and demonstrate relevant cases.

Workshop: change the three arrivals' order and repeat the first record. Worked guidance: under the initial contract, every order ends at 95 and repetition does not change the result. Then add a distinct event also worth 50 and confirm the total increases. Summary: composition must supply missing semantics between components as well as connectivity. Relate the design to data models, rules, reconciliation and recovery.

Define an option as a usable composition

A design option includes product, configuration, extensions, integrations and operating commitments. Individual component compatibility does not establish composition compatibility. Identify constraints all components must satisfy together: platform, interface, availability, support and mandatory capabilities. A future support date should not be treated as support already available at entry into use.

Fictional example: service must start on day twenty in environment B with a compatible interface between product and in-process extension. Product P1 runs on A or B and exposes API X; P2 runs on B and exposes API Y. Extension E1 needs A and X. E2 needs B and Y but becomes available only on day forty. E3 needs B and X and is available now. All remaining support periods, once started, cover the required horizon. There is no API bridge or exception to platform B.

P1+E1 fails the extension platform; P2+E2 fails initial availability; P2+E3 fails API compatibility. P1+E3 satisfies these documented constraints. The business capability motivating the extension still needs demonstration. A reconciliation claim does not by itself establish duplicate handling, writes, partial-failure behavior or recovery under agreed criteria. Those criteria should be part of the option and its assessment before compliance is declared.

Workshop: first retain every constraint and identify the combination that can advance to demonstration. Then change only the entry date to fifty. Which additional combination now satisfies platform, API and availability? Does this automatically demonstrate reconciliation? Finally assess allowing E1 to run on A on a separate machine despite the architecture’s in-process requirement.

Worked guidance: on day twenty only P1+E3 meets the listed constraints. On day fifty P2+E2 is also available and compatible, without establishing functional outcomes. Allowing E1 on another machine changes architecture and interface rather than merely ticking a compatibility box. The connection, contracts and effects of that alternative would need definition, alongside a decision about the original restriction. Compare complete options and evidence status while preserving the distinction between documentary feasibility, testing and acceptance. If dates or support commitments change again, reassess the relevant composition rather than copying the product’s individual status to all its integrations.

Preference ranges and ranking reversals

A weighted matrix can support a recommendation when criteria, scales and weights have agreed meaning. If a weight is still under discussion, reporting the ranking at one point hides its dependence on preference. Analyze the regions in which each option leads, identify ties and distinguish admissibility from position under the chosen function. An option that never leads a function can remain admissible and may not be dominated on all criteria.

Workshop: three fictional admissible options have reliability and adaptability scores, with higher better on both: A=(90,30), B=(60,75), C=(70,50). Score is w×reliability+(1-w)×adaptability, with w between 0.3 and 0.9. The authority has not confirmed the weight. There is no probability distribution for w and no tie-breaking rule. Write the three functions, find the A/B boundary and determine whether C ever leads. The meaning of the scales is accepted only for this exercise.

Worked guidance: A=30+60w, B=75-15w and C=50+20w. Equality between A and B occurs when 75w=45, so w=0.6. B leads below this value and A above it; at the boundary both score 66 and C scores 62. For w≤0.6, B-C=25-35w is at least 4. For w≥0.6, A-C=40w-20 is at least 4. C therefore never has the highest score in the interval. At the endpoints, w=0.3 gives A=48, B=70.5, C=56; w=0.9 gives A=84, B=61.5, C=68.

A does not dominate C on both criteria: it has more reliability and less adaptability. B does not dominate C either: it has less reliability and more adaptability. C's failure to lead under this function creates no new admissibility constraint. If someone wants to value balance, that requires articulating and deciding another preference, rather than inserting an informal criterion after seeing the results.

Produce a conditional recommendation stating the boundary, the unresolved tie rule and the preference decision needed. Counting points on a grid does not establish the probability that an option is best: point selection and density change the count. A weight is a preference in the model, not a probability of product success. Nor does this analysis prove that predicted scores will be achieved; performance evidence still needs assessment.

Preserve option conditions and relationships between views

Evaluate an option as a complete composition, including components, temporary conditions and exit from those conditions. An exception for one component does not automatically extend to every component using the same supplier. Similarly, an information architecture does not preserve meaning merely by using one label in every view. In both cases, the decision depends on retaining the relationships and scope that give it meaning.

Workshop: a fictional rule requires region U for active data and copies. An exception permits only encrypted backups in V for three months. Service lasts nine months. Option J keeps an active cache in V and has net value 80. K keeps only encrypted backups in V, with demonstrated exit to U at the end of month two and deletion of V copies; its value 70 does not yet include the exit cost of 8. M keeps everything in U and has value 60. Determine the preferred option under highest eligible net value.

Worked guidance: J fails because an active cache is outside the exception. K complies with its described transition and is worth 70−8=62. M also complies and is worth 60. Recommending K requires retaining the exit that makes it eligible. Excluding K because it used V ignores the exception; assigning it 70 ignores a necessary cost. A future extension must not be presumed.

In a second workshop, a delivery report closes an order only when its currently requested revision has been accepted by the recipient. V1 was sent and accepted by event E1. Then V2 was requested and sent. A late copy of E1 arrives, still identifying V1. A process retains only the last event received per order, dropping revision and event identity. Explain the error and draw the required relationships.

Worked guidance: retain order, requested revision, event type, identity and accepted revision. The sending view can show V2 sent, historical view V1 accepted, and closure projection V2 still without acceptance. The E1 copy does not change its scope. Deduplicating E1 without retaining revision still permits accepting V2 using a V1 acceptance. Arrival ordering does not turn an old observation into a new decision either. Define checks for sending without acceptance, acceptance of the current revision, late old-revision acceptance and repeated copies. The model demonstrates the agreed projection, not a general guarantee of delivery across systems.

IN PRACTICE

A successful allowed-export test does not demonstrate denial of unauthorized access; include negative criteria in the comparison.

Common pitfalls

Upfront price as total cost; feature counts without criticality; double counting; decimal places as certainty.

Related topics: Measure outcomes and interpret evidence · Remove limitations and increase value

Take this idea with you

Recommend with explicit assumptions and demonstrated necessary capabilities.

Create account

Reference: CBAP Competencies and Proficiency Levels · CBAP six-knowledge-area blueprint, May 2026 handbook

CBAP® is a registered trademark of International Institute of Business Analysis. bigsavant.com is an independent preparation platform and is not affiliated with, associated with, sponsored, authorised or endorsed by IIBA. Content and questions are original, are not official exam questions, and completing our tests does not award or guarantee any certification. Names are used only to identify the subject. All other trademarks belong to their respective owners.