Plan decisions, authority and evidence

Organize analysis work around the decisions to be made, with dependencies, deadlines, authority and verifiable information.

1. Start from the decision and its useful deadline

In a fictional middleware migration, a reservation can be cancelled without cost until Thursday at 12:00. The decision needs eight working hours of review, available from 09:00 to 17:00 with no holidays. Delivering the packet on Wednesday at 16:00 permits completion only on Thursday at 16:00: one hour on Wednesday and seven on Thursday.

Delivery on Wednesday at 12:00 allows five hours that day and three on Thursday, finishing at 12:00. This calculation uses the case’s explicit calendar. An analysis completion date may satisfy a document schedule yet arrive too late to influence the decision.

Record the decision, its last useful date, minimum evidence, time needed to assess it and decision owner. Account for time zones when teams work in different countries; do not resolve them by assuming everyone uses the same local time.

2. Represent dependencies and availability

Two people start independent tasks at 10:00. Confirming the inventory takes two hours; analyzing exceptions takes three. Synthesis takes one hour and starts only after both finish.

Its earliest completion is 14:00, not 16:00: the initial tasks overlap. If a half-hour review can start only at the 15:00 session, earliest approval is 15:30. With a single person whose exclusive attention each task requires, overlap is no longer allowed.

Distinguish precedence, effort and resource availability. Plan near-term work in greater detail and identify what may change after new evidence. This supports controlled replanning without pretending that a sequence drawn before discovery already contains every answer.

Do not confuse a technical dependency between requirements with the availability of the people analyzing them.

3. Specify what an approval permits

A conditional approval may authorize a pilot for version 3 and a defined group, provided an owner confirms reconciliation before Friday at 16:00. Under that contract, the signed document does not authorize version 4, every customer or confirmation after the deadline.

Model the condition as a checkable rule: scope, version, evidence, accepting person and temporal validity. Distinguish funding approval, agreement on requirements and operational acceptance; each answers a different decision. An editorial update with no impact may follow a simple process, but its classification must also follow agreed governance.

If a condition ceases to hold, record the need for a new decision by the appropriate authority. Do not replace that decision with a note that artificially retains approved status.

4. Apply bounded delegations

In the example, the operations owner is absent. Written delegation lets a deputy accept pilots for up to 30 users provided the recovery requirement is unchanged. A 24-person pilot with the same requirement fits; a 24-person pilot with a changed recovery requirement does not.

Headcount and decision type are independent limits. Experience does not automatically create authority, but a valid delegation should not be ignored merely because the principal is absent. If the case requires two independent approvers, one person holding two roles does not count as two people.

Plan who may decide, how conflicts are resolved and what happens when nobody with authority is available. These are local governance examples, not universal CBAP requirements.

5. Preserve context as information circulates

An evidence file may contain restricted data. The committee needs the assessment outcome, but not every member may open detailed records. Plan an approved view showing version, scope, conclusion, limitations and a reference for an authorized reviewer without improperly distributing data.

A link does not establish recipient access or that a screenshot remains current. Retain the relationship between a decision and the information actually reviewed. A conclusion about one consumer on version 3 does not automatically transfer to another consumer or version.

For relevant changes, assess impact before reusing the conclusion. A summary view can be sufficient for the decision if policy and purpose permit; distributing the whole repository is not an objective in itself. If evidence must be inspected again, retain the applicable version in an authorized location.

Keeping only a filename or cryptographic digest of a deleted file does not retain its content. A digest helps compare a candidate copy but does not recover information that no longer exists.

6. Measure analysis work with useful denominators

The team returned 12 of 40 packets in one window and 15 of 100 in the next. Absolute counts increased, but the proportion fell from 30% to 15%. That describes the two samples.

Attributing the difference to a new checklist would require assessing changes in scope, difficulty, criteria and team, among other relevant explanations. Define the observed unit before comparing: returned packets, corrected requirements and rework hours are different measures.

If a packet returned three times, a proportion of affected packets counts it once; a correction-cycle measure may count three events. Use confirmed causes to guide improvements. Delayed reviewer assignment calls for a different response from contradictory rules discovered during review.

The first may call for reassigning reviewers; the second may change how rules are confirmed. For an effort measure, classify why work occurred. If nonoverlapping categories total 80 drafting hours, 20 planned-review hours, ten defect-correction hours and ten approved-new-requirement hours, total effort is 120.

The defect-correction fraction is 10/120, about 8.33%. A legitimate scope change does not become a defect merely because it followed the first version.

7. Choose investigation that can change the decision

There are 90 minutes of expert time before signing a non-cancellable solution contract. A 60-minute session resolves whether the solution meets a mandatory recovery limit; reviewing a visual model takes 30; confirming a color preference takes 30.

The visual model can be revised later without material cost. The recovery constraint can eliminate the option before signature. Under these assumptions, reserve the 60-minute session first and use the remaining 30 on the task best supporting the immediate decision.

If valid evidence already established recovery, repeating the session might cease to be a priority. Investigation value depends on what remains unknown and which decisions it can change. Do not assign automatic priority to the largest document, the most senior stakeholder or the task with most missing pages.

8. Exercise: build a plan that enables a decision

Produce a table with five columns: decision, evidence, dependencies, owner and deadline. The 24-user pilot retains the recovery requirement; the deputy has the delegation described in this lesson. Inventory and exception analysis start at 10:00 with different people and take two and three hours.

Synthesis takes one hour after both. The approval session starts at 15:00 and lasts 30 minutes; the reservation expires at 16:00. The packet contains restricted records and policy permits an approved summary view.

Solution: synthesis finishes at 14:00, the decision can finish at 15:30, delegation covers the pilot and the view must retain version, scope and limitations. Schedule feasibility does not establish that the pilot will be approved: evidence may justify refusal.

For the international meeting, distinguish “ready for decision”, “conditionally approved” and “authorized to execute”, explaining each state’s concrete condition. International variant: a session at 18:30 on a UTC+8 clock corresponds to 10:30 UTC; another at 12:00 UTC+1 corresponds to 11:00 UTC.

With 30 minutes each and 30 minutes of synthesis after both, delivery can occur at 12:00 UTC without reserve. These offsets are fixed in the exercise; for a real calendar, confirm offsets on the meeting dates.

Distinguish procedure outcome from authorized criterion

Decision governance should define who decides, the criterion and what happens when that criterion produces no choice. Voting until one name remains is a procedure; it does not by itself establish that the name meets another rule, such as defeating every alternative in direct comparison. Also document who may change the method and how that change is approved.

Consider three people ranking X>Y>Z, Y>Z>X and Z>X>Y. Each person has a coherent preference order. In direct comparisons, X defeats Y by two votes, Y defeats Z by two, and Z defeats X by two. No alternative defeats both rivals. Eliminating X/Y first and then comparing with Z ends at Z; starting with Y/Z can end at X. The procedure produces a result, but agenda order influences which result.

These rankings are ordinal: they express preference, not difference intensity or comparable distances between people. Assigning points to positions can be a legitimate approved rule, but it is not an automatic consequence of the rankings. Similarly, authority to convene a meeting or select its sequence does not necessarily include authority to change the criterion.

Workshop: calculate every comparison and repeat elimination under three starting orders. Write a record preserving preferences, identifying the impasse and requesting a decision from the competent authority. Propose how a future rule will address cycles, ties and nonparticipation without claiming consensus. Summary: a sound process exposes limits and distinguishes an authorized decision from an outcome produced by a convenient sequence.

Assess delegation over cumulative scope

Delegation needs a unit, scope and application conditions. “Up to twenty participants” might mean concurrently active people, people ever enrolled or places in one session. These three contracts produce different decisions. Use the agreed definition and reconcile identities before comparing with the cap. Do not turn a cumulative rule into a per-form rule merely because teams divided the work.

Fictional example: authority permits at most twenty distinct people ever enrolled while retaining recovery policy. History contains twelve people. X proposes nine, three already in history, adding six. Y proposes seven: two historical people, two of X’s six newcomers and three not present elsewhere. X alone reaches eighteen; Y alone reaches seventeen. Their combination reaches 12+6+3=21. Authority to approve either isolated request does not establish authority to approve both.

The decision record should preserve its baseline, identities or reconcilable references, approvals already changing scope and remaining delegation conditions. The second decision should not reuse an old baseline as if the first did not exist. Changing approval order does not change the final union. If the rule is historical, ending participation also releases no authorization capacity; an active-person rule would need a different definition.

Workshop: assess Y after X. Then consider removing one of the three otherwise absent people from Y. Finally consider removing only one of Y’s two people also included among X’s newcomers. In each variant calculate resulting scope and determine whether the deputy can decide under the twenty-person cap. Assume no changes to recovery.

Worked guidance: X followed by Y reaches 21 and exceeds delegation. Removing a person exclusive to Y reduces the union to twenty, meeting the inclusive numerical cap. Removing only an identity still present in X leaves the union at 21. Change must affect genuinely authorized scope, not merely delete a duplicated form row. Even the twenty-person variant still requires checking recovery and any other mandate conditions. The committee considers scope exceeding delegation; this analysis does not predict that the committee will approve it.

Retain approval objects and context

A short reference such as “approve row 4” is interpretable only within its document and version. Removing content, translating, renumbering or combining sources creates a review object that may differ from the original. Information-management planning should preserve relationships between these objects, the material actually presented and the decision’s scope. A signature or receipt can bind a decision to an object without establishing approval of everything in its source.

Fictional example: O2 has an exception in row 4 and the general rule in row 5. Shareable V2 removes the exception and renumbers the general rule as row 4. Minutes approve “row 4 of V2.” The original has restricted access; V2 may circulate within the team. Interpreting the minutes as approval of O2’s exception uses the same number for different content. Authorizing an auditor to read O2 does not change the object decision makers approved.

Retain version identifiers, bytes or another demonstrated reproduction mechanism, source-to-derivative references, the applied transformation and the link between minutes and reviewed object. A digest can help confirm the identity of available bytes; it cannot recover missing bytes or explain the transformation. This example’s policy requires exact reconstruction and understanding of origin. Other contexts may impose different policies; the example establishes no universal retention period.

Workshop: the archive proposes keeping O2, minutes and V2’s hash while deleting V2 and its transformation map. No other copy or reproducible recipe exists. The team suggests granting full original access to compensate for the loss. Identify two gaps that remain and propose an alternative preserving access separation.

Worked guidance: the exact reviewed material and the mapping explaining why row 4 means different things are lost. Expanding access recovers neither and may conflict with the existing restriction. Retaining V2, mapping, minutes and a verifiable O2 link permits reconstruction under appropriate permissions. Any new decision on the exception should explicitly identify the relevant object and version; it should not retroactively broaden old minutes. Availability, integrity, transformation and authority require related records but are not the same property.

Exercise files

Original Python 3.10+ exercise without dependencies: compatibility, block costs, working calendar and international sessions. Includes editable data, instructions and worked results.

Download the decisions and transitions exercise

SHA-256 (ZIP)

b59f5925c46322fecef4bd4a4271bd777be9b72ef32644873ab6103b104fac65

IN PRACTICE

A packet delivered on time for a committee may arrive too late to cancel a reservation. The useful deadline depends on the commitment and review time.

Common pitfalls

Planning only documents; adding tasks that run in parallel; forgetting reviewer availability; extending approval scope; counting roles as independent people; comparing totals without denominators; attributing causation without evidence.

Related topics: Change strategy · Analysis governance

Take this idea with you

The analysis plan should get sufficient information to a person with authority while the decision can still have its intended effect.

Create account

References

CBAP® is a registered trademark of International Institute of Business Analysis. bigsavant.com is an independent preparation platform and is not affiliated with, associated with, sponsored, authorised or endorsed by IIBA. Content and questions are original, are not official exam questions, and completing our tests does not award or guarantee any certification. Names are used only to identify the subject. All other trademarks belong to their respective owners.