Reconcile actual and remaining work
A forecast must state what each component includes. If actual cost is forty thousand and thirty-five thousand remains, including a twelve-thousand open order, the total is seventy-five thousand. Adding the order again creates double counting. Comparing the result with a seventy-thousand budget shows a five-thousand forecast overrun. The forecast is not capped by authorized funding; it should show the best available estimate. Handling variance depends on existing authority and owner decisions, without assuming that every forecast update needs fresh approval.
Compare costs against the same baseline
During migration, the old service may remain active while the new one already incurs expense. In the example, the old service’s eight thousand monthly remains for two months and the new service adds five thousand monthly. Total cost is twenty-six thousand; the increment over keeping only the old service is ten thousand. Identify horizon, units, and assumptions before comparing options. Automation releasing ten internal hours likewise does not establish cash reduction if payroll remains unchanged. Report released capacity and later check how it was used.
Measure progress under the agreed rule
Deliverable count may be an unsuitable progress measure when weights differ. The exercise assigns twenty percent to design, fifty to migration, and thirty to recovery, counting only accepted outcomes. With design and recovery accepted, fifty percent is demonstrated. Calling migration almost ready does not permit inventing partial credit. This rule is an explicit case convention, not a universal measurement standard. At the committee, show the rule, each deliverable’s state, and the evidence supporting reported acceptance.
Preserve options until the decision
A decision made after its deadline can lose the alternative it intended to approve. If a support reservation expires Tuesday at noon and the regular committee meets Thursday, use the authorized extraordinary route. Prepare two comparable options: delay five days without extra cost or approve eight thousand in support to retain the date. Include acceptance, dependencies, cost, and required authority. A favorable technical opinion helps assess the option but does not automatically grant funding authority to the PM. The recommendation should clarify the choice without prematurely incurring an unauthorized obligation.
See work outside the invoice
A vendor may keep its price unchanged by transferring tasks to RUN. Before calling the proposal free, identify those tasks, required skills, capacity, and commitments that would be displaced. Confirm who accepts ownership and include dependencies in the plan. Apply the same care at closure: a nonblocking improvement may transfer to another owner if criteria permit, but the proposed name needs acceptance and resources. The final report should preserve the action and follow-up rather than deleting it or keeping the project open without a reasoned decision.
Guided practice: a clear request in English
Calculate the lab figures and write the requested decision. Forecast is seventy-five thousand against a seventy-thousand budget; accepted progress is fifty percent. If the date depends on support not yet approved, do not rely only on a green label. A useful message asks for a decision by tomorrow between delaying five days without extra cost and approving eight thousand to retain the date. Confirm the outcome and record conditions, ownership, and plan updates. The summary connects evidence, alternatives, and authority without confusing recommendation with approval.
Synthetic steering exercise / Exercício fictício de decisão
actual = 40; remaining_including_open_order = 35
forecast = 75; budget = 70; forecast_variance = 5
open_order = 12 # already inside remaining; do not add again
coexistence_total = 2 * (8 + 5) = 26
baseline_cost = 2 * 8 = 16
incremental_cost = 10
accepted_weight = 20 + 30 = 50%
Please decide by tomorrow: delay five days at no extra cost,
or approve EUR8000 support to retain the date.40 thousand actual+35 thousand remaining=75 thousand; an included 12-thousand order does not increase the total to 87 thousand.
Common pitfalls
Counting orders twice, using activity as acceptance, treating capacity as cash, or taking a decision to committee after its option expires.
Related topics: Capacity and dependencies · Governance and suppliers · Handover to RUN
Reporting should enable decisions using comparable data, explicit conditions, and enough time to execute the chosen option.
Reference: PM²-PM Highlights · PM² reference practices and cloud operational governance; primary guidance reviewed 2026-09-30