1. Prepare the decision from the delivered solution
Requirements approval establishes a reference; acceptance of the developed solution concerns what was delivered. Prepare the second decision using the candidate version, demonstrated scope, results against criteria and known gaps. A list of green tests with no connection to the commitment may not answer stakeholders' questions.
In a fictional middleware replacement, decision makers need to know whether agreed processing, recovery and operation were demonstrated for the proposed version. Summarize what meets criteria, what remains unresolved and which options the applicable authority can choose.
Include a recommendation and its rationale so each decision maker need not reconstruct the entire technical history. Keep detailed evidence accessible for those who need to inspect it. The analyst organizes these connections and facilitates the decision; a well-presented package does not automatically transfer solution acceptance authority to them.
2. Obtain decisions covering the necessary responsibilities
Identify which responsibilities acceptance requires in the project's context. Business confirmation of functional outcomes may not cover an operational obligation reserved for APS. Conversely, operational approval does not resolve disagreement over expected user behavior.
The package should show who decides each matter and how those decisions compose the outcome. This lesson's exercises state the rule explicitly; an actual project must confirm its applicable governance. Do not require a signature from every contributor when the rule designates representatives with sufficient authority.
That can delay an already valid decision without adding coverage. When a representative is absent, use the provided delegation after confirming scope and validity. A meeting with many attendees is not itself a complete decision.
What matters is coverage of the required responsibilities for the same acceptance object.
3. Define the effect of an accepted limitation
A known limitation can receive different treatment depending on its nature and available authority. If the rule allows a presentation discrepancy to be accepted, the owner can do so with explicit scope, rationale, action and timing. That decision must not be extended to a mandatory control the same rule does not permit to be waived.
Nor should every limitation be presumed to require rejection of the whole solution. Present options within actual boundaries: correct before acceptance, accept a permitted limitation or defer the decision. Clarify whether a condition must be met before deployment or may be tracked afterward.
“Accepted subject to demonstrated recovery” does not establish readiness while that demonstration is missing. Record an observable condition and who confirms it. Pressure from a maintenance window may justify bringing decision makers together quickly, but it does not independently change the meaning of the condition they approved.
4. Connect acceptance to the version that will proceed
The decision must identify the solution it covers. If the version changes after sign-off, check whether the change affects scope, criteria, evidence or decision conditions. Not every difference requires repeating every test; impact analysis may justify reusing valid evidence and confirming only the affected part.
However, a “small patch” label does not establish equivalence. In a fictional example, R9 was accepted with a tested queue configuration and recovery behavior. R10 changes those queues' retry policy.
The R9 package does not automatically decide R10 even if the supplier retains the commercial name. Identify the difference, obtain the appropriate assessment and route the decision for the current reference. Preserve the earlier decision rather than retrospectively changing the version it names.
This makes each point-in-time decision understandable and prevents history from appearing to demonstrate an assessment that never occurred.
5. Communicate what can proceed and what remains conditional
A solution can be accepted while still awaiting an authorized deployment window. Sign-off is a relevant input to proceeding, but other project conditions may remain applicable. In one exercise, Business and APS accept R9; operational authorization permits deploying R9 only on Monday between 22:00 and 23:00.
Communicate both facts: the solution is accepted and execution is planned within that window. Do not turn approval into an instruction to execute immediately or describe acceptance as nonexistent because the window has not arrived. Use statuses preserving these distinctions and identifying the next action.
After deployment, follow value measurement with the assigned owners. Acceptance of demonstrated behavior does not guarantee all savings forecast in the business case. The handover to operations should make the decision outcome, continuing conditions, follow-up ownership and support reference clear.
6. Workshop: prepare the acceptance record
Fictional conditions: R9 demonstrated matching for the complete test population and recovery in 18 minutes against a 20-minute limit. Business may accept presentation differences and accepts an abbreviated label with a later correction and owner.
APS confirms operational criteria. The rule requires these two decisions; both identify R9. A separate authorization permits deploying R9 on Monday between 22:00 and 23:00.
The supplier proposes replacing R9 with R10, which changes retry behavior after a timeout and has not been assessed. Write each version's status, the immediate action and the limitation that must remain in the record. Worked reasoning: R9 has valid acceptance under the stated conditions, with the accepted label and follow-up action; preparation for its authorized window can proceed.
R10 needs change analysis, applicable evidence and a corresponding decision. Retain R9 as an available alternative if technically usable and within authorization. Do not extend sign-off to the new behavior or automatically reopen every decision without assessing impact.
Exercise: acceptance, preparation and a feasible interval
In an independent example, the window is 18:00–19:00. A run may last from 18 to 23 minutes and the plan must support any duration in that range. Data becomes ready at 18:07; preparing configuration B takes four minutes after readiness.
Business and APS accepted the same production version/configuration B, allowing starts from 18:15. Recovery covers 18:05–18:42. Configuration C is newer but lacks APS acceptance.
Before reading the solution, list entry conditions and calculate every possible start, including endpoints. Solution: B has decision coverage; C does not. B’s earliest start is max(18:00, 18:07+4, 18:15, 18:05)=18:15.
Its latest is min(19:00−23, 18:42−23)=18:19. Thus [18:15,18:19] is the complete interval. Minimum duration does not determine the last safe start; at 18:20 a 23-minute run exceeds recovery by one minute.
Counterchecks: if APS allows starts only from 18:20, the interval becomes empty; if recovery is confirmed until 18:47, the latest start becomes 18:24; if data becomes ready only at 18:16, four-minute preparation also makes the original interval empty.
None of these changes erases earlier acceptance: it changes current feasibility or proposal scope. At work, record version, configuration, environment, decision owners and conditions, readiness, justified duration and execution/recovery intervals.
Establish whether each condition applies at start or throughout execution; recovery must cover the whole run here. Check approval coverage first, then intersect time limits. Present admissible choices to the owner while keeping proposal, decision and execution separate.
If a maximum duration is unsupported, do not invent it to obtain a favorable interval.
Guided practice: versions, limitations and acceptance options
First exercise. V7 was accepted and V8 changes a mandatory field. Business explicitly signed for both versions; APS signed V8 conditional on a recovery channel that remains available. Changed-field tests have not been performed. A presentation exception permits an abbreviated label but does not waive the mandatory field. What is missing? Evidence for the changed condition. Neither existing signatures nor the exception substitute for that demonstration. Inventing a missing Business signature is also incorrect because it expressly covers V8.
Keep a table of object, version, condition, owner and evidence. If the channel disappears before execution, another blocker arises independently of the pending test. If the changed-field test passes, it resolves the evidence gap without restoring a channel that has been removed. V7 history remains as observed. Record updates should follow the actual change without erasing everything or transferring everything automatically.
Second exercise. A permitted limitation may be accepted now at cost 2q+3, in units already made comparable; delaying costs 11. Workload q may range from two to six without probabilities. Acceptance ranges from seven to 15. Options tie at q=4; acceptance costs less below and delay less above. An explicit minimize-worst-cost rule would choose delay, but does not make it cheaper in every case. The decision owner may request workload confirmation or choose a decision criterion; the analyst presents the consequences of that choice.
Summary: preparing acceptance requires demonstrated conditions, respected mandates and explained consequences. Dossier quality depends on answering the current decision rather than accumulating files or silently choosing a preference for the owner.
Exercise files
Three parts with fictional rules, data, editable templates and worked reasoning. Practice baseline, condition, version and pilot decisions. Open the files in an editor; no program execution is required.
Download the approval and acceptance workshop
SHA-256 (ZIP)
e1c1e5637288de11d296303f27311ce09aced911b5ab03cc176f5a5e5c9f6f9b
R9 accepted, deployment authorized for Monday and R10 awaiting a decision are compatible states.
Common pitfalls
Requirements approval as solution acceptance; sign-off transferred between versions; a missing condition as a completed action; acceptance as immediate execution or guaranteed benefit.
Related topics: Agreement on the requirements baseline · Requirements plan and responsibilities · Planned traceability and acceptance
Obtain a valid decision on the demonstrated version and communicate its effect without extending its scope.
Reference: PMI-PBA Examination Content Outline · Five-domain ECO / verified 2026-10-01