Concept and mechanism
Comparing options requires common criteria and enough information for a decision. Distinguish mandatory conditions from weighted preferences and make uncertainty in effort, cost, and benefit explicit. The most desired option may depend on an interface unavailable for the release.
Analyze dependencies before promising a feature set. A baseline records what was accepted, in which version, and under which conditions; it does not mean needs can never change. Rejected or deferred requests retain their rationale and, where relevant, a condition for reassessment.
The approval process should identify who can accept the commitment, including operational impacts. Voting can help explore preferences but does not remove previously defined responsibilities.
Guided application
In an exercise, a release has capacity for ten days. Feature A needs six days and an additional four-day interface; B needs five and is independent. Promising A and B as eleven days ignores that A needs ten in total and the combination needs fifteen when efforts are additive and no work is shared.
Compare feasible options and value instead of silently removing the dependency. After selection, use prototypes, examples, and review to validate understanding and complete criteria. If a prototype was accepted by day-shift users, do not assume it covers on-call exceptions.
Record the evidence limit and arrange the missing review. Baseline approval should reflect what was actually agreed, not what the team hopes others will accept later.
3. Separate importance, eligibility and allocation
A ranked list identifies needs considered more important under the chosen criteria. It does not prove the first items fit together in a release. A valuable capability may require another that is unavailable; a mandatory condition may apply before any use; and a decision may depend on information still unconfirmed.
Keep these questions separate: what has value, what is permitted, what is feasible and what was actually selected. A Must classification needs context: mandatory for which outcome and by when? If every item is genuinely mandatory in this release, confirmed effort is twelve person-days and only ten are available, ranking does not resolve the gap.
Present the incompatibility so an applicable authority can revisit a condition or another permitted solution can be considered. Do not silently reduce an obligation to a preference to make the table fit. Nor should deferral become rejection: retain its reason and review condition.
4. Count a shared dependency once
In this independent model, A needs four person-days, B three, and both require the same component P, needing three person-days. P is built once, is compatible with both and has no other associated work or independent value. A alone costs seven; B alone six; together they cost 4+3+3=10, not thirteen.
A’s agreed value is eight units and B’s seven. Only in this exercise, effects do not overlap and combined value is additive: fifteen. Independent alternative C costs nine and is worth thirteen.
With capacity ten, no other limits, no partial execution and permission to leave capacity unused, A+B+P has the highest value among these options. The dependency is neither omitted nor charged twice. In a real project, confirm that the component is genuinely shareable, whether integration adds work and whether benefits can be added. Calculation is useful only within those definitions.
5. Check the set even when a ratio looks persuasive
Consider another example unrelated to A, B, C or P. X needs six person-days and is worth twelve units; Y and Z each need five and are worth nine each. Items are independent and indivisible, values additive, capacity ten and no other criteria apply.
X has the highest value-to-effort ratio: 12/6=2 versus 9/5=1.8. Selecting X first leaves four days and prevents adding Y or Z, producing value twelve. Y+Z uses ten days and produces eighteen.
Individual ratio ranking did not find the best set in this model. This does not make ratios useless in every context; it shows why they should not be presented as universal guarantees. For a small list, enumerating sets allows transparent checks of dependencies, capacity and value.
For larger problems, choose an appropriate technique while retaining explicit assumptions, limits and decision criteria.
6. Respect capacities that cannot be exchanged
A third example provides ten engineering person-days and six QA person-days. R needs five engineering and four QA; S needs four engineering and four QA. R+S uses nine engineering days, within capacity, but eight QA days, exceeding its limit by two.
The capacities should not be added to announce sixteen interchangeable days: skills and availability were defined separately. The unused engineering day does not replace two QA days under the stated conditions. Assess each constraint and identify permitted adjustments with their own estimates and commitments.
This example measures effort by role, not calendar duration. Showing that a set fits aggregate capacities also does not establish that all precedences, access windows or daily availability fit the promised date. The planning lesson distinguishes effort, duration and entry conditions; use that analysis before turning a set feasible in this model into a delivery commitment.
7. Review priority when its rationale changes
A capability was deferred while an interface was missing. When that interface becomes available, the review condition has been reached; the capability does not automatically move to first place. Reassess current value, resources and commitments.
Similarly, a priority based on a use ending Friday may lose value if the earliest delivery is Monday. Confirm the consequence stated in the case instead of retaining an estimate conditional on timely delivery. Do not invent another use to justify the old preference.
When a set is chosen through the agreed process, record its version, accepted capabilities, dependencies, deferred items, assumptions and decisions still conditional. If two options have equal modeled value and both satisfy every defined criterion, acknowledge the tie; calculation does not authorize inventing a winner.
An additional agreed criterion or a decision by the mandated person may be needed.
8. Workshop: recommend a package without hiding its conditions
Return only to the A/B/P/C model in section four. Prepare a table for A+P, B+P, A+B+P and C, showing effort, value and feasibility. The respective answers are seven and eight; six and seven; ten and fifteen; nine and thirteen.
Each fits the capacity of ten, and A+B+P has the highest modeled value. Adding C to any of them exceeds capacity. The decision note should explain why P is counted once and why values can be added.
If Business chooses the recommended set within its established mandate, record the baseline and conditions for revisiting the choice when effort, value or dependencies change. A valid decision need not be requested again. If an independent QA limit emerges, the earlier conclusion may require review.
Summary: clear criteria, complete sets, explicit constraints and a traceable decision. This worked answer demonstrates only this fictional model, not a real production plan.
9. Compare sets when benefit depends on the state
Neither a set’s cost nor its benefit is necessarily a naive sum of its items. Count shared preparation once and identify overlapping business outcomes as well. In an independent example, D requires four engineering person-days and one QA day and is worth 12 in both S1 and S2.
E and F each require three engineering days and one QA day; they need the same preparation G, requiring one engineering day and one QA day. G does not yet exist and has no independent benefit. E is worth 11 in S1 and six in S2; F is worth five in S1 and ten in S2.
Together, E and F include three units of the same benefit in each state. Capacity is seven engineering and three QA days, with no transfers. E + F + G uses 3 + 3 + 1 = 7 and 1 + 1 + 1 = 3; net benefits are 11 + 5 − 3 = 13 and 6 + 10 − 3 = 13.
D fits and is worth 12; E + G and F + G fit with minimums six and five. Combining D with any other item requires eight engineering days including G, so it does not fit. If the mandate maximizes minimum benefit across these two possible states, E + F + G wins by 13 against 12.
Do not compute a mean without justified probabilities. Sensitivity: if confirmed overlap increases from three to five units, the same set remains feasible but is now worth 11 in both states; D becomes the best option under this criterion. The choice changes because of net benefit, not item count.
In real work, state where the possible states come from, benefit boundaries, evidence of sharing and decision authority. This is a fictional decision model, not evidence of realized benefits. Summary: build complete sets, check every capacity, avoid double counting and apply the agreed decision criterion.
Integrated applications: options, decisions and measures
Solve the seven situations under their own rules. For each, write the supported decision, one failing alternative and the condition that would change the conclusion.
1. A costs three and is worth five; B costs two and is worth four. Either requires one shared two-unit interface. Independent C costs three and is worth six. At capacity seven, A+B costs seven and is worth nine; B+C costs seven and is worth ten; A+C costs eight and does not fit. B+C is the best permitted set. At capacity eight, A+C becomes feasible and is worth 11. Changing capacity can change selection without invalidating the historical decision.
2. Common preparation takes one day. The external decision arrives on day three and chooses a two-day or four-day variant; later activation takes one. Possible finishes are days six and eight. Guaranteeing day seven for the four-day branch requires the external decision by day two with preparation complete. Identifying that condition does not authorize the team to impose a date on the external owner. Continue permitted work and show the conditional commitment.
3. An ineligible option never enters weighting. Among eligible options, B has usability 50 and economy 90; C has 90 and 70. With usability weight w, B=90−40w and C=70+20w. They tie at one third. A weight interval 0.2–0.6 contains different preferences, requiring a weight or another decision rule. Check endpoints and one value on each side of the threshold; using only the favorable endpoint conceals sensitivity.
4. A rejected option cost nine when seven was available. There are now 11, but its new version needs an additional four-unit dependency, totaling 13. Another complete option costs eight. Retain the old reason and open current comparison of both scopes without automatic approval. If evidence establishes that the dependency is unnecessary for the selected version, the calculation changes; separate procurement alone does not remove it.
5. Baseline is X1/Y1. X2 was applied at ten. Y2 is approved for 11 after X2; Z is merely proposed. At 10:30, baseline is X2/Y1. At 11, once the second change is applied, it becomes X2/Y2 without Z. A package containing Z establishes no decision on it. Distinguish a future-approval record from actually applied state.
6. Delegation until 16:00 permits eight effort units and requires Risk concurrence for data changes. The option costs seven; its owner signs at 15:40 and Risk at 16:05. Decision completion did not occur during the mandate. Compare Risk at 15:50: completion occurs then and, if the rule preserves completed decisions, execution may follow 16:00. Advisory voting does not resolve missing required concurrence.
7. An objective requires confirmation within 120 seconds. Raw cross-clock difference is 123 and final-clock offset relative to the initial clock is two to six: true duration is 117–121, still unresolved. Better evidence bounds offset to three through six: duration is 117–120, now compliant. A fast initial acknowledgement still measures another event. Summary: reliable decisions preserve cost, authority, version and timing-evidence scope. At work, expose what was established and what remains conditional.
Exercise files
Four parts with editable data, response templates and worked reasoning. Practice representation, value and feature selection with dependencies and team limits. Optionally use the Python 3 calculator.
Download the stakeholder and priority workshop
SHA-256 (ZIP)
75c2593d20ad6d8af320fe845f969b068067386430245388be009079d5d54caf
A with its dependency costs ten days; A plus B costs fifteen under the exercise conditions.
Common pitfalls
Omitted dependency; voting treated as universal authority; partial approval treated as full coverage.
Related topics: From need to solution scope · Value, stakeholders, and business case · Requirements plan and responsibilities
Accept or defer requirements with explicit value, feasibility, and authority.
References
- Requirements management planning and benefits evaluation · PMI-hosted2014 conference paper;practitioner perspective,not universal process
- PMI-PBA Examination Content Outline · Current linked five-domain ECO; copyright 2013, not an inferred new launch date
- Collaborative and creative business analysis · PMI-hosted2014 conference paper;practitioner concepts,not mandated method
- Business Analysis Standard: Requirements and Designs Life Cycle Management task cards · Public Business Analysis Standard task cards v2.0, copyright2025