Plan the change workflow

Define intake, triage, transitions and commitments that keep requests visible and ready for decisions.

1. Several channels can feed a coherent record

A request may arrive through a meeting, email or work tool. The plan should explain how communication becomes a trackable record: who registers it, what information makes the proposal understandable and how the sender receives its reference.

Banning every channel except one is unnecessary if a reliable recording process exists. In a fictional example, Business requests an earlier close and APS sends a message about the same proposal. These may contribute to one request while retaining both origins and concerns.

Conversely, two messages titled “change close” may propose different days or consumers. Plan confirmation of identity and intent before merging records. Message count does not equal the number of distinct changes.

If a proposal evolves, preserve differences relevant to whoever analyzes it. Organized intake should reduce context loss without demanding information impossible to know before analysis itself.

2. Define each state's meaning and exit condition

Received may mean only that a record exists. Ready for analysis may require an identifiable proposal and a contact for clarification. Analyzed may mean impacts were documented while a decision remains pending.

Choose enough states for actual work and define transition owner, evidence and next recipient. In a fictional workflow, analysis ends when it includes proposed behavior, dependencies, alternatives and known impact; uncertainty may remain explicit.

The decision maker may accept, reject or request further information under agreed rules. An information request should neither disappear from the queue nor return as a history-free request. Approval also does not establish implementation: it may depend on a window or confirmation of a dependency.

These states illustrate a design, not a mandatory PMI sequence. Their usefulness is showing what happened and what remains, avoiding “closed” for different decisions and outcomes.

3. Classify by effect and mandate

The plan may allow spelling corrections through a simple route and require different analysis for behavioral changes. The criterion should be explicit. Correcting a letter in a heading, with no effect on identifiers, contracts or meaning, may fit documentary delegation.

Replacing “business days” with “calendar days” changes a condition even though only two words change. Edited text size does not measure impact. It also helps to distinguish restoration of approved behavior from a request for a different capability during an incident.

If an authorized operational procedure permits recovery of known configuration, that action follows the applicable mandate. Changing the service commitment to prevent future failures is a separate proposal requiring its own analysis and decision.

Link records sharing an origin without turning the incident into unlimited authorization. Classification should route work to those able to decide and act while preserving what the simpler route permits without adding an unrequired committee.

4. Specify what the deadline actually promises

A four-hour acknowledgement target does not promise completed analysis or implementation. Define starting event, ending event, calendar and waiting treatment. In this exercise, the team works Monday to Friday, 09:00 to 17:00, with no holidays in one time zone.

Four working hours after Monday at 15:00 end Tuesday at 11:00. If a different rule pauses counting when information is requested Monday at 16:00 and resumes it on receipt Tuesday at 10:00, the deadline becomes Tuesday at 13:00: one hour was consumed before the pause and three remain.

Do not apply a pause unless the rule exists. Record start, suspension, resumption and reason when these conditions belong to the agreement. An exceeded target should trigger the defined action, such as communicating delay or reallocating analysis; it does not mean approval by silence unless an applicable explicit rule actually provides that.

5. Make team handoffs visible

A sent task is not necessarily a task received by someone able to execute it. The workflow needs to identify who owns the next step, what happens when information is missing and how the sender sees that situation. In an international example, APS completes analysis and sends a link to a mailbox with no owner available for two days.

“Analyzed” may be accurate, but the decision has no operationally available recipient. Plan coverage, authorized substitution and target handling; an alternative recipient is not automatically a new approval authority. At implementation handoff, retain decision conditions, proposal version and any time limits.

If a condition expires, the queue should not treat approval as current authorization merely because the request number stays the same. A short report can distinguish requests waiting for information, a decision, a window or outcome confirmation. That distinction supports action on the cause of waiting.

6. Workshop: separate recovery, proposal and document correction

Prepare a table of request, route, next owner and completion evidence for three fictional situations. A: during a failure, an authorized operational procedure restores approved configuration. B: someone proposes accepting instructions after the close cutoff to reduce future rejections.

C: the document owner may correct a heading typo without changing meaning, identifiers or contracts; that absence of effect was confirmed. Worked reasoning: A follows the defined operational route, retaining the record and recovery confirmation; B is recorded and analyzed as a change to agreed behavior; C may follow the simple delegation with correction history.

If B arose during A, link its origin without transferring recovery authorization to the new commitment. Add that “received within four working hours” does not promise a decision in that period. Exercise the workflow with a duplicate request, an incomplete response and an expired implementation condition.

Identify the part of the plan addressing each situation before selecting a tool.

Count time without duplicating suspensions

Exercise: working time is 09–12 and 13–17 on weekdays, with no holidays in this example. The target is four hours and receipt is Wednesday at 10. A opens at 11 and closes at 14. B opens at 13:30 and closes at 15. Counting pauses while either is open. Calculate by segments before reading the solution. Wednesday 10–11 contributes one hour. Suspension persists from 11 to 15; lunch is already outside working time. Then 15–17 contributes two hours and Thursday 09–10 supplies the fourth. The deadline is Thursday at 10.

Summing raw A and B durations duplicates overlap and includes nonworking time. Closing A does not resume counting because B remains open. Restarting at 15 loses the valid earlier hour. At work, preserve individual request events, the applicable calendar and suspension rule. Confirm whether a partial reply closes a request or merely adds information: follow the contract without inferring closure from a message. Check overlapping pauses, holidays, lunch and receipt near closing time. Summary: the clock is the intersection of working time and absence of active blockers.

Guided application: one proposal, multiple deliveries

Intake uses source and number as identity and increasing revision to supersede parameters. Client C/8 revision 3 arrives, followed by C/8 revision 2 and an identical copy of revision 3. D/8 revision 1 also arrives. All share a title. First draw two current records, one per identity, and link deliveries to their corresponding history.

C/8’s current state is revision 3 in any ordering of these deliveries. D/8 stays separate. There are two requests, not four requests or one global request numbered eight. The identical copy can be recognized as a repeat while retaining necessary receipt data. No revision rule by itself grants authority to execute a proposal.

As a variation, another C/8 revision 3 message arrives with different parameters. It is no longer an identical copy: there is a same-revision conflict requiring clarification with the source before choosing current content. Do not simply choose the last arrival to conceal conflict. If a proposal is withdrawn, retain an explicit withdrawal decision instead of inferring withdrawal from absence in a partial list. At work, this discipline prevents confusion among retries, corrections and different consumers. Summary: identify intention, version and decision separately; preserve history without counting it as new intentions.

Exercise files

Three parts with briefs, reference records, editable templates and worked reasoning. Practice retirement dependencies, working-time targets and concurrent revisions. Open the files in an editor; no program execution is required.

Download the context, change and document workshop

SHA-256 (ZIP)

a1ca47e3e4fa32dd1f8a37da7530dddf5fec94b5f0a556bc81a942a22ab89272

IN PRACTICE

Four working hours from Monday at 15:00 end Tuesday at 11:00 under the exercise 09:00–17:00 calendar.

Common pitfalls

Confusing receipt with decision; merging matching titles without comparing proposals; turning delay into approval; using an urgent route beyond its mandate.

Related topics: Context and analysis decisions · Documents, concurrent work and references · Requirements plan and responsibilities

Take this idea with you

The workflow should explain who does what, with which information and under which conditions.

Create account

References

PMI-PBA® and PMI® are registered trademarks of Project Management Institute, Inc. bigsavant.com is an independent preparation platform and is not affiliated with, associated with, sponsored, authorised or endorsed by PMI. Content and questions are original, are not official exam questions, and completing our tests does not award or guarantee any certification. Names are used only to identify the subject. All other trademarks belong to their respective owners.