← PMI-PBA: needs, requirements, and benefits
22 / 37 · 120 MIN

Relevant costs and comparison horizons

Compare alternatives on the same scope while separating future costs, existing resources, funding constraints and benefit timing.

1. Build a common basis before adding values

A migration request can arrive with three apparently comparable proposals: retain middleware, upgrade its version or move the application to another service. Before calculating, state the outcome the business needs and the operating conditions.

Options must cover the same relevant scope, including support, recovery, interfaces and retirement of old components where applicable. An installation price excluding operation is not directly comparable with one already including three support years.

Record currency, horizon, starting point and inclusions. In this lesson, amounts are fictional, services are equivalent under the stated conditions, and calculations exclude discounting, taxes and inflation unless explicitly stated. These simplifications support studying the decision; they do not replace a real project’s financial conventions and requirements.

2. Separate history from costs the decision can still change

The initial study cost twelve thousand euros, already paid and unrecoverable whichever option is chosen now. That amount belongs in project history but does not differentiate future alternatives. Charging it only to the option abandoning the original proposal artificially favors continuation.

The useful question is which costs and outcomes the decision can still change. A future cancellation fee can matter; a refundable deposit can also have different consequences across options. Do not classify everything already paid as irrelevant without checking recoverability and alternative use.

Keep historical expenditure visible in project monitoring, separately from the incremental comparison. The sponsor can then understand both how much has been spent and which alternative better uses remaining resources. Classification erases neither accountability nor accounting records.

3. Identify alternative use of an existing resource

The application can use equipment the organization already owns. Its historical purchase cost was ten thousand euros and cannot be reversed. An authorized, feasible sale for four thousand is now available only if the application does not use the equipment.

Using it means foregoing that four-thousand alternative even without another acquisition payment. Distinguish opportunity cost from cash outlay: the former helps compare resource uses; the latter supports cash and budget planning. Do not automatically add the historical ten thousand and foregone four-thousand sale as two new payments.

Also establish that the alternative is achievable, including timing, authorization and necessary transaction costs. An imagined valuation without a buyer or feasible alternative use does not become recoverable value merely by appearing in a spreadsheet.

To compare A, which uses the equipment and requires eight thousand in future spending, with B, which requires fourteen thousand and permits the four-thousand net sale, choose a consistent basis. Future cash gives A=8 and B=14−4=10. An opportunity-cost basis charges A=8+4=12 while B=14.

A costs two less in both presentations. Adding four to A while also subtracting the same four from B counts the resource difference twice, artificially reversing the choice.

4. Include transition, maintenance and retirement

Over a common twelve-month horizon, retaining the service costs four thousand euros monthly and requires a six-thousand mandatory upgrade, totaling fifty-four thousand. Migration costs eighteen thousand for preparation, two thousand monthly for all twelve months, three thousand additional coexistence cost and six thousand for retirement at the end, totaling fifty-one thousand.

Additional amounts are not included in monthly fees, and this exercise has no other flows. The projected difference favors migration by three thousand without turning the difference into approval. Omitting retirement yields forty-five thousand and exaggerates the advantage; omitting the baseline upgrade yields forty-eight thousand and changes the conclusion.

Ask each owner to confirm estimate scope: FinOps may know consumption, APS support and another team decommissioning work. No isolated total guarantees inclusion of all these elements.

5. Find when the comparison changes

Another comparison uses thousands of euros and m complete service months. A costs 5 + 3m; B costs 17 + m. Equality occurs when 5 + 3m = 17 + m, giving m=6.

At three months, A costs fourteen and B twenty; at twelve, A costs forty-one and B twenty-nine. The cheaper option depends on the horizon even when both provide the same service. If allowable duration ranges from four to eight months, do not claim B is always cheaper.

Show both sides of the switching point and identify who can clarify likely duration or the decision policy under uncertainty. Do not invent a uniform probability distribution for the interval. Equal cost at six months also establishes no equality in risks or characteristics omitted from this model.

6. Separate total advantage, funding and benefit timing

An option can cost less overall while requiring more money before operation. If migration needs twenty-one thousand initially and the authorized limit is twenty thousand, its projected three-thousand advantage over the horizon does not remove the initial constraint.

Present the funding gap and alternatives for the decision owner to assess. Benefit timing also needs to be explicit. If actual expenditure reduction begins at the start of month four and amounts to two thousand monthly, months four through twelve comprise nine months and eighteen thousand, not twelve months and twenty-four thousand.

Check whether the saving is already reflected in a lower cost line to avoid counting it again as an additional benefit. A schedule change is not neutral merely because the monthly amount stays unchanged.

7. Explore uncertainty that can change the recommendation

In the twelve-month example, migration costs forty-five thousand before retirement. If retirement can cost between four and ten thousand, total cost ranges from forty-nine to fifty-five thousand. Retaining the service costs fifty-four thousand.

Migration is cheaper when retirement costs less than nine thousand, ties at nine thousand and costs more above it. This interval establishes no guaranteed advantage but identifies relevant information to collect. If an inspection establishes a maximum of eight thousand under applicable conditions, total cost is bounded at fifty-three thousand and the cost ranking becomes stable within that scope.

A cost margin proves neither risk acceptance nor satisfaction of other conditions. Nor does it justify unlimited investigation: information’s usefulness should be compared with the cost and time needed to obtain it.

8. Exercise: prepare a traceable recommendation

Prepare a summary before reading the solution. The baseline costs fifty-four thousand over the year. Migration costs forty-five thousand before retirement, which remains between four and ten thousand.

It requires twenty-one thousand immediately against an authorized limit of twenty thousand. The twelve-thousand study has already been paid and is unrecoverable under every option. Solution: the future comparison excludes the common study while retaining it in history.

Migration ranges from forty-nine to fifty-five thousand, so it can cost less or more than the baseline. The retirement switching value is nine thousand. A separate initial funding gap of one thousand exists.

The recommendation should expose the estimate needing greater precision and the required funding decision. Presenting the midpoint of fifty-two thousand as an observed cost or authorization to start is insufficient.

Compare relative loss in each state

An independent exercise has two possible states without probabilities. Total costs are A=(30,50), B=(38,42), C=(45,45). Every option meets mandatory constraints.

Policy selects minimum maximum regret. Solve before reading: the first-state benchmark is 30 and the second-state benchmark is 42. Regrets are A=(0,8), B=(8,0), C=(15,3).

A and B tie at 8; C has 15. This policy alone does not resolve the tie. Minimum maximum cost would select B at 42, but that is another rule.

If a confirmed extra cost of 1 applies only to A in the second state, A’s maximum regret becomes 9 and B wins at 8. If supplier credit is conditional, first calculate correct cost in each branch, then the benchmark. At work, record horizon, future flows, constraints, permitted states and decision rule.

Preserve the same states when comparing options; do not compare one option’s best state with another’s worst as if that were a feasible joint observation. Common paid costs change neither relative losses nor available funding. Summary: cost, regret, probability and cash answer different questions; document which question governs the recommendation.

Compare alternatives over the same horizon

First exercise: an asset bought previously for 20 can be sold today for five or leased for one year. Leasing receives six, pays one and leaves sale value one at year-end. Use a 20% discount rate; uses are exclusive and amounts share one currency unit. Leasing present value is (6−1+1)/1.2=5, equal to immediate sale. Internal use with no residual and initial payment two displaces opportunity worth five, not ten. Comparable economic cost is seven and new payment two. If lease residual rises to four, that alternative is worth 9/1.2=7.5; opportunity changes although historical price does not.

Second exercise: A costs 4+2m. B costs 10+max(m,4), plus four on exit if m<6. For integer months one to eight, inspect each branch. At four months A costs 12 and B 18; at five, 14 and 19. At six the charge disappears and both cost 16. Afterward B is lower. Unlike a jump directly from more expensive to cheaper, equality occurs at an admissible horizon here. An algebraic root is valid only within the branch that produced it.

At work, separate past payments, new outflows, alternative receipts and residual values. Align dates before comparison and record exit conditions, minimums and exclusivity. These fictional assumptions do not replace analysis of an actual contract. Summary: relevant cost depends on available alternatives, horizon and conditions, not merely a monthly fee or historical price.

Guided applications: branch costs and reserve over time

Compare cost and then liquidity, keeping the questions separate. First, A costs 6+4m and B costs 18+2m with additional termination eight when the integer horizon is below seven months. From four through six, A−B=2m−20 is negative. From seven onward, A−B=2m−12 is positive. Thus A wins from four through six and B from seven through nine in the considered range. At six, costs are 30 and 38; at seven, 34 and 32. There is no admissible tie. The formula omitting termination suggests a tie at six but uses the wrong branch. A horizon range supplies no probabilities.

Now assess an unrelated alternative: initial cash 15, minimum reserve three, payment ten on day 0, payment four on day 2 and receipt five on day 4. Balances are five, one and six. The largest reserve shortfall is two on day 2. Two additional units available before that payment would suffice, producing balances seven, three and eight. Annual advantage four does not create those funds on day 2. No additional funding is authorized in the current plan, so feasibility remains unresolved.

Variation: receipt five moves from day 4 to the start of day 2, before payment. Post-event balances become five, ten and six without a reserve breach. Timing changed, not total flows. Proposed acceleration belongs in the forecast only when supported. Summary: compare a common horizon, apply contractual conditions to the correct branch, and check each liquidity date; a lower-total-cost option can remain infeasible under permitted timing.

Exercise files

Original Python exercise with editable data, instructions and worked reasoning on costs, horizons, funding, scales, weights and uncertainty. Requires Python 3.10 or later.

Download the costs and decision-criteria exercise

SHA-256 (ZIP)

41930a254c429a113b80b788aa567f85128aa86443ff1216b5f72a92c34e8ed7

IN PRACTICE

In the model 5 + 3m versus 17 + m, equality occurs at six months. The same option is not cheapest across every horizon.

Common pitfalls

Different horizons; historical expenditure charged to only one option; owned equipment treated as having no alternative use; omitted retirement; double-counted savings; intervals treated as probabilities; total advantage confused with available funding.

Related topics: Business case, benefits and needs · Decision criteria and sensitivity

Take this idea with you

A useful comparison shows what can still change, when costs or value occur and which assumption can alter the preference.

Create account

References

PMI-PBA® and PMI® are registered trademarks of Project Management Institute, Inc. bigsavant.com is an independent preparation platform and is not affiliated with, associated with, sponsored, authorised or endorsed by PMI. Content and questions are original, are not official exam questions, and completing our tests does not award or guarantee any certification. Names are used only to identify the subject. All other trademarks belong to their respective owners.