From purpose to entry condition
The fictional Vega project replaces a batch platform. The agreed outcome is reconciled positions by 06:00; installing servers is a necessary deliverable, but does not establish that outcome. At the integrated review, start by connecting each deliverable to intended use and the criteria for moving to the next activity.
A completed installation may still need security acceptance before receiving test data. If that review is missing from the schedule, the installation-to-test relationship is incomplete. Record owner, duration, entry condition, and completion evidence.
An approved milestone expresses a commitment; it does not automatically create the capacity or approvals needed to meet it.
Logic, duration, and availability
Use a small model before discussing schedule compression. A takes two days; then B takes five and C takes three, with independent teams; D takes two and waits for both. Without other constraints, duration is nine days: 2 + maximum(5, 3) + 2.
Adding all durations gives twelve and ignores permitted parallel work. Now add a different condition: B and C exclusively require the same person. In that second model, the person needs eight days after A, and minimum duration becomes twelve.
Both answers are consistent with different assumptions. Confirm resources, calendars, and dependencies before presenting the date as a commitment; arithmetic alone is not a probabilistic forecast.
Capacity and knowledge belong in the plan
A three-person team has 105 weekly hours in this scenario. RUN uses 63, absence uses 14, and knowledge transfer uses seven; these reservations do not overlap. That leaves 21 hours, not 42, for project activities.
A request for 28 hours requires resolving a seven-hour gap through scope, timing, or authorized capacity. Do not assume learning fits outside working hours or that a video equals independence. Before supplier departure, have RUN execute and validate recovery in a rehearsal environment with agreed conditions and support available.
Record questions and tasks still requiring assistance. This evidence informs both team readiness and the feasibility of the transition date.
Authority, versions, and communication
The integrated review also checks that documents describe the same solution. If the schedule uses architecture B while the financial forecast still uses A, individual signatures do not establish a coherent plan. Reconcile licensing, startup sequence, tests, and risks against the proposed version.
Separate technical opinion from budget authorization: the architect may recommend the solution without authority to commit additional person-days. Also clarify decision communication. In an international project, “Friday at 5 p.m.” needs a date and time zone; silence is not approval when explicit response is required.
The meeting summary should identify the decision, authority, conditions, owner, deadline, and acknowledgment. Escalate through agreed limits with options and the impact of delay.
Workshop: commitments, conditions and capacity
Set aside twenty minutes to prepare a Vega plan-review sheet. Use columns for outcome, dependency, forecast, commitment and evidence. All figures and limits in this exercise are fictional. Solve it individually and then ask another person to look for a missed condition. The deliverable is the sheet with calculations, decisions and outstanding matters; it is neither lab execution nor validation of a real environment.
The agreed outcome is reconciled positions by 06:00. Record installed servers as an indicator of a necessary deliverable without presenting it as sufficient proof of the outcome. Identify responsibility for installation, operation and reconciliation, and how each team confirms the dependencies it receives. Sharing a vision does not require removing useful local indicators.
In the duration model, A takes two days. B takes four and C takes two, both after A and in parallel with independent teams. After C, a mandatory three-day wait precedes D. D takes one day and waits for B and C’s waiting period. Calculate 2 + maximum(4, 2 + 3) + 1 = 8 days. Draw both branches: waiting can overlap B but still constrains D. Explain why adding three days to the seven-day duration of the model without waiting gives a different and incorrect forecast under these assumptions.
The team has eighty hours. RUN reserves forty, already including eight for knowledge transfer, and absences consume ten additional hours. Thirty hours remain. Project demand is 32 hours of interchangeable work: the gap is two. Do not subtract the eight transfer hours again or return them to project capacity. Identify an option for resolving the gap and who must confirm it. If that option requires a specific skill, also check that person’s availability; the aggregate balance alone cannot answer that new condition.
For knowledge transfer, one operator has already recovered the service independently but will be absent during the first week. The others have only watched a recording. Retain her evidence and plan to observe people who will actually be available, addressing gaps before supplier departure. Similarly, three booked nonconsecutive nights do not satisfy a rehearsal requiring three consecutive nights with preserved state. Distinguish reservation confirmation from suitability for the method.
Finally, architecture B changes the startup sequence. Its license is demonstrably covered by the current contract. Update the financial plan’s correspondence without inventing a second purchase, and review dependencies and rehearsal criteria. The authority replied to the request: “Received; I will decide after review.” Record confirmed receipt and a pending decision. Close the sheet with an explained forecast, commitments still required and the next action for each outstanding matter. Do not turn calculations, received messages or valid licenses into authorizations that were never given.
Workshop: a plan executable with available information
An integrated plan connects work to when decisions, resources and evidence become available. Finding dates that fit after learning an outcome is insufficient. Combining the lowest cost from one alternative with the shortest duration from another is insufficient too. The communicated combination must correspond to an executable way of working.
Five-minute exercise: work starts on day 1. At the end of day 3 a pilot reveals whether solution A or B is needed. Each requires two preparation days followed by two execution days. The proposal prepares only the correct solution on days 2 and 3 and executes on days 4 and 5. Explain the problem without assuming the pilot already ended. Choosing on days 2 and 3 depends on future information. A feasible schedule for each known scenario is not a policy the team can follow before knowing the scenario. Waiting puts preparation on days 4 and 5 and execution on days 6 and 7. Earlier information, preparing alternatives with confirmed capacity or revising commitment are options to assess rather than already authorized facts.
Second exercise: installation takes two hours followed by one validation hour. Evidence remains valid three hours after completion and must cover delivery throughout 14:00–15:00 UTC. Compare starting installation at 08:00 and 10:00. The first validates at 11:00 and loses validity after 14:00; the second validates at 13:00 and stays valid until 16:00. Earlier is not always better when a fixed window meets expiring evidence.
Finish with a table recording each condition, when it becomes known, owner, capacity and failure effect. Include contingencies sharing one person and assess joint activation. Keep effort estimates, elapsed duration and authority to alter commitments distinct. Connect the table to schedule, risk, capacity and forecast communication lessons.
Workshop: integrate cash, milestones and authorizations
An integrated plan needs a sequence executable across every relevant dimension. One team performs three nonoverlapping jobs. A takes two days, costs six at start and receives eight at completion; B takes one, costs five and receives six; C takes one, costs four and receives five. With initial cash five, A cannot even start. B first leaves six at the end of day one; A can then run through day three, leaving eight; C finishes on day four. If B must finish by day two and A by day three, this sequence meets both milestones. Starting with C then B preserves cash but delays A until day four.
Construct a table of start, payment, completion, receipt and balance. Do not use receipts before they occur or confuse total profit with the ability to fund each start. Do not add parallel capacity when the model explicitly excludes overlap. Immediate receipts are an exercise premise; in actual work, confirm the event that makes receipts usable.
Integration goes beyond numbers. A validated V2 configuration is not automatically covered by a license signed for V1. A support roster approved for Monday does not cover Sunday merely because a manager advanced an internal date. These are two independent conditions: configuration identity and coverage on the actual date. Preserve already-valid testing and training, but reconcile each commitment with its controlling authority. Returning to Monday may resolve support while leaving the license unresolved.
Use eight minutes to enumerate all six job orders and reject each alternative violating cash or a milestone. In the remaining seven, prepare an opening-condition list with version, date, authority and evidence. Deliver an executable plan and an explicit list of remaining conditions. Traps include validating budget and schedule separately, extending authorizations by analogy and repeating valid work instead of resolving the missing condition. Connect this to budgeting, resource management and operational readiness.
Build a plan before knowing the branch
A contingent plan must show what is committed before the outcome is known and what can wait for information. In a model, the partner responds at time two. If it accepts, delivery arrives at three and integration finishes at four. If it declines, the internal alternative takes four and can finish at six. Internal availability, however, is guaranteed only by a reservation paid at time zero. Enough duration on paper does not replace that availability.
With reservation two, additional internal execution four and partner price five, build two branches. Acceptance: reservation two plus partner five, total seven and finish four. Refusal: reservation two plus execution four, total six and finish six. A budget of seven in each branch and deadline six are compatible with reserving first and choosing execution later. Reservation cost remains even when the alternative is unused. Starting internal execution immediately may close the partner option if the conditions make the two executions incompatible.
Use the same method for qualitative commitments. A V1 license does not establish V2 authorization; a response to a request is not approval; technical delivery does not imply usable customer access. Record each condition as satisfied, pending or incompatible, with its authority and timing. Preserve valid technical results while resolving missing dependencies.
Exercise: change internal availability so reservation is required only at time two. Recalculate which commitments can wait and which costs remain necessary. Then suppose the partner response arrives at three: the four-unit alternative finishes at seven and the plan no longer ensures deadline six. The lesson is to expose information timing, capacity reservation and execution in every branch without turning an external forecast or intention into a confirmed commitment.
Linked case: a migration with conditional decisions
Spend about 30 minutes on this fictional case. At each stage, record the known state, available decision, responsible authority and next evidence needed before comparing with the worked answer. All three stages concern the same project, but an earlier decision does not automatically turn a later condition into a fact. This written exercise is neither an official question set nor a timed exam section.
Stage 1. A team is migrating a booking service to V2. Preparation ends at the end of day 2. Validation takes two full days after preparation. One team performs both activities and works on every numbered day. Operations signed coverage for launch on day 5, conditional on successful V2 validation and recovery within 30 minutes. Management approved funding. A V1 rehearsal recovered in 18 minutes, but V2 has not been rehearsed. Write the earliest technically possible date and distinguish funding, coverage and technical acceptance.
Answer 1. Validation can occupy days 3 and 4, allowing day 5 to be proposed if the results meet the criteria. Funding and conditional coverage are recorded; V2 technical acceptance remains pending. The V1 result does not establish recovery of the new version. The PM follows up the evidence and decision conditions without deleting valid approvals or announcing a guaranteed launch.
Stage 2. On day 4, V2 functional validation succeeds, but recovery takes 42 minutes. The team identifies a correction requiring one workday and another recovery rehearsal. The project rule allows only the risk owner to accept an exception to the limit. No exception decision exists. Operations confirms that coverage for day 5 does not automatically extend to another date. Management asks whether the earlier funding decision permits launch. Write a response and two decision options, identifying the dependencies still open.
Answer 2. Funding approval does not remove the recovery condition. One option is to obtain and record the risk owner's exception decision while keeping the 42-minute result visible. Another is to correct, rehearse again and confirm coverage for a new date. The case supplies neither the new rehearsal duration nor the next operations window, so it does not support an exact new date. Requesting an exception also does not mean it was accepted.
Stage 3. The correction is complete and a new rehearsal on an identified V2 configuration demonstrates 24 minutes. Operations accepts the day 7 window in writing. Before launch, another configuration change is proposed but not applied. The rule requires assessing changes' effect on evidence before using it as a decision basis. State what to retain and what needs another decision.
Answer 3. Retain the 24-minute rehearsal with its applicable configuration and the acceptance of day 7 coverage. Assess the proposed change: if it alters relevant assumptions, the changed configuration needs the required evidence before launch; if deferred, the rehearsed configuration can remain under consideration subject to the other conditions. Do not destroy a valid record or automatically transfer its validity to another configuration. Deliver a table showing version, result, window and authorization state at all three stages. A common trap is treating approval with a defined object and conditions as permanent permission.
# Synthetic deterministic planning model, not a production schedule
parallel = 2 + max(5, 3) + 2 # 9 days
exclusive = 2 + 5 + 3 + 2 # 12 days
project_hours = 105 - 63 - 14 - 7 # 21
gap = 28 - project_hours # 7Vega books configuration from 18:00 to 20:00 and testing from 20:00 to 22:00. The specialist becomes available only at 19:00. Without authorized substitution or compression, the earliest decision supported by the rehearsal is at 23:00.
Present the variance and alternatives instead of retaining an infeasible time.
Common pitfalls
Adding parallel branches; overlooking exclusive resources; treating probable availability as a reservation; confusing recommendation with approval; removing learning from effort forecasts.
Related topics: Plan with real capacity · Stakeholders, mandates, and cross-team decisions · Operational exit and controlled decommissioning
An integrated plan connects outcome, logic, capacity, versions, and authority. Turn assumptions into commitments only when enough evidence exists.