← PMP: project decisions in a production context
04 / 25 · 80 MIN

Measure value and hand over autonomy

Interpret indicators and close the project with acceptance evidence.

Read performance

Planned value represents budgeted work scheduled; earned value represents budgeted work completed; actual cost represents expenditure. CPI = EV / AC and SPI = EV / PV. An index below one signals unfavorable performance in that dimension. Forecasts should explain their assumptions.

Acceptance and continuity

An operational delivery includes access, monitoring, instructions, recovery, and ownership. A team that can demonstrate diagnosis and recovery provides stronger evidence than an emailed document. Confirm acceptance, open items, and the owner of post-project benefit measurement.

Guided application

Interpret indicators before choosing actions. EV=40 and AC=50 produce CPI=0.8: cost exceeds measured earned value. The index does not identify the cause.

An EAC=BAC/CPI forecast applies only when assuming continuing cost efficiency; with BAC=100 thousand euros, EAC=125 thousand. A detailed remaining-work estimate may justify another model. At closure, distinguish installation, operational acceptance, and realized benefit.

Request demonstration of access, diagnosis, and recovery; assign remaining work and benefit measurement. The project team may finish while adoption and outcome evaluation continue under an agreed owner.

Indices without inventing delay days

With EV=40, PV=50, and AC=40 in the same monetary unit, CPI is 1 and SPI is 0.8. EV−PV is −10 in that unit, not ten days. To understand the finish date, connect earned-value interpretation with the network, progress, and remaining work.

Do not swap denominators or use favorable cost performance to conclude schedule compliance. Each indicator addresses a different aspect of project status.

Closing with continuing accountability

Closure does not require eliminating every future obligation. In a fictional case, a warranty can continue after the project if governance permits closure and an owner explicitly accepts follow-up, resources, and conditions. Apply the same care to residual risk: document acceptance by an authorized owner, its limits, and future review.

Handover may be gradual when the rules permit it. If RUN already performs routine tasks independently, reduce support for those capabilities while retaining coverage for an undemonstrated recovery procedure. Before the team leaves, confirm document access in an authorized repository.

Accepting the new application does not establish that consumers, archives, and recovery arrangements allow decommissioning the old one.

Choose the forecast and preserve units

Start by identifying the date, scope and unit of every figure. In an independent example, EV=60, AC=75 and PV=80, in thousands of euros. CPI=60/75=0.8 and SPI=60/80=0.75. The first compares earned value with expenditure; the second compares earned value with planned value. Neither automatically converts variance into delay days. Forecasting a date requires linking progress to remaining activities, resources and dependencies. Nor do the indices explain cause: higher cost may arise from several mechanisms requiring their own evidence.

Now consider BAC=180 and a revised estimate of 90 for all remaining work. With AC=75, the forecast based on that estimate is 165. Assuming continuing historical efficiency of 0.8 instead would give BAC/CPI=225. Do not choose the most favorable number: explain which assumption applies and what supports the model. A forecast does not itself change the approved budget.

As an exercise, discover that the 90 excludes a recovery check costing 12. The estimate no longer represents all remaining work: correct it to 102 and forecast 177. If the 12 were already included, adding it again would double count. Before presenting the result, check completeness and overlap between components. Record the changed assumption, estimate owner and factors that could change it.

Close delivery while keeping measurement executable

Acceptance should demonstrate the role the team will perform after project exit. A support team may need to diagnose and escalate without authority to perform a restore. In that case, exercise access and routing with the identity it will actually use and confirm who receives the escalation. A rehearsal dependent on the account of someone leaving may hide a gap. Do not confuse autonomy with assigning every privilege.

Closure may also leave future obligations, such as warranty follow-up or benefits measurement. Confirm that the rules permit transfer and that ownership, capacity, access and timing are accepted. Naming an owner does not automatically reserve time from analysts who extract data. Once those dependencies are resolved, the whole delivery team need not remain merely because a benefit will be measured later.

When interpreting results, check population mix. In an exercise, the initial period has 60 simple requests at three minutes and 40 complex requests at nine: an average of 5.4 minutes. The next period has 90 simple and ten complex requests at the same times: an average of 3.6. Aggregate improvement does not demonstrate faster handling within either type. Compare equivalent groups and record changes in demand. As guided work, write a conclusion distinguishing accepted delivery, secured measurement capability and benefit still to be demonstrated; state who collects the data and when the conclusion will be reviewed.

Handover rehearsal: dates, boundaries and dependencies

Prepare a handover record with three columns: condition, available evidence and remaining action. In one exercise, the current team ends coverage Thursday at 20:00 and the new owner starts Friday at 08:00. Both signatures do not fill the intervening twelve hours. An acceptable resolution is to confirm transitional coverage for that period or adjust departure and current-team coverage. Merely postponing the closure ceremony does not create availability. Ask the learner to identify who accepts coverage, what capability they need and how they will be contacted.

Add risk acceptance limited to 80 requests per minute when forecast load rises to 90. The record should preserve the 80 limit and request a decision about 90 before presenting acceptance as applicable to the new load. An already scheduled monthly review does not authorize expansion. A response may reduce load or alter protection but needs evidence and a decision about the new conditions.

Finally, the manual was copied to a shared repository but links three attachments to the departing person’s account. Identify all three, transfer custody through the authorized process, update links and verify access using the receiving identity. The resolution demonstrates availability of required material, not execution of every instruction. Summarize accepted responsibility, effective coverage, applicable risk boundaries and accessible knowledge separately. Mark each condition satisfied only when evidence matches the identity, date and scope that operations will use.

IN PRACTICE

A project has EV of 40 person-days and AC of 50. CPI = 0.8. If that efficiency continues, a total budget of 100 person-days forecasts 125. Explain the causes and recovery options.

Common pitfalls

Treating CPI as a diagnosis; closing without autonomy or benefit ownership.

Related topics: Suppliers, contracts, and acceptance · Quality, data, and benefits

Take this idea with you

The project delivers value when the outcome is accepted, operable, and measured.

Create account

Reference: Earned Value Management: A Guide to Reading the Numbers · PMP ECO July 2026

PMP® is a registered trademark of Project Management Institute, Inc. bigsavant.com is an independent preparation platform and is not affiliated with, associated with, sponsored, authorised or endorsed by PMI. Content and questions are original, are not official exam questions, and completing our tests does not award or guarantee any certification. Names are used only to identify the subject. All other trademarks belong to their respective owners.