Concept and mechanism
A decision tree separates controllable choices from uncertain outcomes. For each option, calculate each branch’s cost or benefit and weight it by the relevant probability. In the teaching example, A costs EUR30,000 with a 25% chance of another EUR20,000: expected cost is EUR35,000.
B costs EUR34,000 without that addition, so it minimizes expected cost within this model. The conclusion does not prove universal superiority of B; other objectives and consequences may change the decision. Sensitivity analysis helps identify which data and assumptions change results most, guiding evidence gathering and response investigation.
Guided application
Avoid precision unsupported by data. Three observations do not by themselves justify a probability reported to two decimal places. Explain origin, ranges or scenarios, and test whether the decision changes.
For explicitly independent events with 20% probability each, the probability of at least one is 1 − 0.8 × 0.8 = 36%; adding 20% and 20% counts the intersection twice. For reserve, distinguish total from difference: if base cost excluding reserve is EUR400,000 and total-cost P80 is EUR460,000, the difference is EUR60,000.
Check that both use the same scope, reserve is not already included, and funding decisions follow defined authority.
Compare value, limits, and risk attitude
Two paths with equal expected loss can have very different consequences. One option may cost twenty thousand with certainty; another may lose one hundred thousand in 20% of outcomes and zero otherwise. Both average twenty thousand, but only one exposes the project to the hundred-thousand outcome.
If a mandatory limit is below that loss, equality of means does not resolve admissibility. Even without that limit, the organization may prefer greater predictability. State criteria and avoid imposing your personal preference on the sponsor.
A utility function can represent agreed preferences, but should not be invented to justify a choice already made. Consider relevant future costs and execution conditions while separating money already spent and unrecoverable.
A reserve derived from P80 still allows outcomes above the modeled value; it is not maximum-cost insurance.
Common pitfalls
Forgotten fixed cost; small sample with false precision; improper probability addition; double-counted reserve.
Related topics: Choose and execute responses · Monitor, close, and hand over to operations
Check units, branches, assumptions, and criteria before recommending an option.